蒸养流水化作业T梁预制厂的探索及研究

2020-10-20雷照

价值工程 2020年28期
关键词:高速公路工艺施工

摘要:高速公路梁厂的规划建设、产梁效率直接影响项目总体目标及施工组织的落实,在高山深谷地段等受限的地形条件下建设T梁预制厂,对规划及布局的要求较高。本文结合漳武高速公路南靖段A3合同段桥梁所处的地形、地貌特点,对一种采用蒸汽养生工艺的T梁预制厂进行探索、研究、改进,缩短梁片预制工期,提高施工效率。

Abstract: The planning and construction of the highway beam factory and the efficiency of beam production directly affect the overall project goals and the implementation of the construction organization. The construction of a T-beam precast factory under restricted terrain conditions such as high mountains and deep valleys requires high planning and layout requirements. This paper combines the topography and landform characteristics of the A3 contract section of the Zhangzhou-Wuping Provincial Expressway, and uses steam curing technology to explore, study and improve a T-beam prefabrication plant, so as to shorten the prefabrication period of beams and improve construction efficiency.

关键词:山区高速公路;高山深谷;地形受限;蒸汽养生;移动台座;液压模板

Key words: mountain expressway;high mountain and deep valley;restricted terrain;steam curing;mobile pedestal;hydraulic template

中图分类号:U445.4                                      文献标识码:A                                  文章編号:1006-4311(2020)28-0240-03

1  工程背景及施工技术难点

漳武高速公路南靖段A3合同段全线共8座桥梁,总长3790m。桥梁均位于高山深谷地段,地形高差在35~90m,桥址区山体自然坡度45~90°,周边地类均为农保地和生态林。根据桥梁周边的地形地貌,经项目部技术人员多方调查论证后确定桥梁征地界外不具备建设T梁预制厂的施工场地。考虑桥高和地形限制,梁板无法由预制变更为现浇。

桥梁上部构件采用预制T梁,其中30mT梁530片,40mT梁408片,38mT梁5片,T梁顶面横坡为-5~5%,且30/40mT梁及±5%的横坡在各桥均为交错布置。结合全桥而言,梁型及横坡多变,传统的梁厂及T梁模板无法满足施工需求。

项目全线路基总长1546m,共分为11段,其中最短长度为9m,最长长度为320m,宽度26m。全线仅K32+580~K32+900段路基长度、宽度具备建设梁厂的条件,此段路基可设30m制梁台座16个,40m制梁台座12个。按照总体施工组织,需设制梁台座34个,路基场地面积不满足要求。

路基纵坡2.9~3.1%之间,纵坡大,在路基上直接建设梁厂,门式起重机吊重行走安全风险极大。……