火电厂主厂房土建施工技术分析
2017-09-25舒欣闫佳萍��
舒欣 闫佳萍��
【摘要】火电厂主厂房建设质量好坏不单单会影响到火力发电机组,还会对火电厂的社会效益及投资效益带来巨大的影响。所以解决火电厂的主厂房的土建施工建设问题,是一项不可懈怠的工程。本文首先分析了火电厂主厂房土建施工的特点,然后分析了火电厂土建施工质量控制存在的问题,最后详细阐述了火电厂主厂房土建施工技术要点,以供同行参考。
【关键词】火电厂;主厂房;土建施工技术
Analysis on Construction Technology of Main Building of Thermal Power Plant
Shu Xin,Yan Jia-ping
(China Energy Construction Group Shanxi Electric Power Construction Co., LtdTaiyuanShanxi030012)
【Abstract】The quality of the main powerhouse of the thermal power plant will not only affect the thermal power generating units, but also will have a great impact on the social benefits and investment benefits of the thermal power plant. So to solve the main power plant of the thermal power plant construction of the construction problem is a non-slack of the project. This paper first analyzes the characteristics of the main construction of the main powerhouse of the thermal power plant, and then analyzes the existing problems in the quality control of the civil engineering construction of the thermal power plant. At last, the technical points of the main construction of the main powerhouse of the thermal power plant are expounded for reference.
【Key words】Thermal power plant;Main plant;Civil construction technology
1. 前言
近几年来,随着电力工程建设的投资力度不断增加,我国就以建立一批“高性能、高产量、高质量”的火电厂为主要的目标,这样才能更好的适应经济发展对电能供应的具体要求。同时由于土建工程的施工质量会直接影响火电厂建设,而主厂房是火电厂生产的主要区域,所以一定要采用影响的措施解决厂房施工常见的问题,这是必不可少的。
2. 火电厂主厂房土建施工的特點
目前国内的火电厂主厂房土建施工建设水平比较一般,主厂房的基础建设大多采用的是灌注桩同基础相互结合的基础建设,也有部分火电厂主厂房采用的是打入桩与独立台阶基础筏板相结合的基础建设。对于主厂房的上部结构柱距也是有一定的规定要求的,必须要满足高度在十米以上,对于层高则要求达到六米,煤斗层的层高要求需要达到十米以上方可。主厂房的屋盖通常是由大型钢架与轻质复合温彩钢板组合搭建而成的,在屋盖的架构上一般都会安装较多的设备埋件,框架主梁上一般都配有尺寸达到二十八米之多的双层筋,上面的箍筋间距要求达到一定的紧密程度。……