大型水轮发电机无功不足的原因分析与处理

2017-05-11毛肖郭思哲王庆平和丽芳

价值工程 2017年15期

毛肖+郭思哲+王庆平+和丽芳

摘要: 本文以云南省华坪县与四川省攀枝花市的交界处观音岩电厂为例针对发电机额定励磁电流不能带额定无功功率的问题进行了相关研究。并对现场情况和机组无功不足可能产生的原因进行分析,通过仿真、计算、对比、验证,得出了“相同励磁电流的情况下,机端电压升高与定子漏抗增大都将导致机组的无功出力大幅下降”的结论,并为此类电厂的今后的运行和发展提出重要的建议。

Abstract: In this paper, a case analysis of Guanyinyan power plant at the junction of Huaping County in Yunnan Province and Panzhihua City in Sichuan Province whose rated field current of the generator can not produce rated reactive power. In addition, the paper analyzes the scene condition and causes of reactive power shortage, through simulation, calculation, comparison and verification, to obtain the conclusion that "Under the same excitation current,increase of terminal voltage and the stator leakage reactance will cause unit reactive power output fell sharply." Finally, some suggestions are put forward by this paper for the future operation and development of this kind of power plant.

关键词: 无功出力;励磁电流;定子漏抗

Key words: reactive power;field current;stator leakage reactance

中图分类号:TM312 文献标识码:A 文章编号:1006-4311(2017)15-0094-03

0 引言

观音岩水电站为金沙江水电基地中游河段“一库八级”水电开发方案的最后一个梯级水电站,位于云南省华坪县与四川省攀枝花市的交界处,装机容量300(5×60)万千瓦。单独运行时保证出力47.8万千瓦,年发电量122.40亿千瓦时,年利用小时4080小时;在上游龙盘水库投入运行后,保证出力139.28万千瓦,年发电量136.22亿千瓦时,装机年利用小时4540小时。工程概算总投资为306.96亿元。2015年底观音岩电厂出现#1发电机额定励磁电流不能带额定无功功率的问题,这不仅使得机组的设备水平降低,而且因电站欠发无功,将使得观音岩电厂每年的电费收入减少。因此,研究发电机无功出力不足的问题,在技术经济上都有着现实意义。

1 对#1机组无功出力不足的原因分析

1.1 现场情况分析

觀音岩电厂#1机组自投产以来,一直存在无功出力不足问题。根据现场提供的数据:“中调下发I母电压设定值为543.8kV;……