颍河取水口围堰及取水穿堤自流管防渗处理施工的技术要求

2016-09-30李传名聂杰汪菊

建筑科技与经济 2016年1期

李传名 聂杰 汪菊

摘 要:颍河取水口工程围堰内外水位差大于8.0m,在本市水利工程建设中很少遇到,又跨汛期施工,施工条件十分恶劣;穿堤自流管的防渗采用截渗墙及压密注浆相结合的措施,达到了预期处理效果。本文通过对该工程设计技术交底的介绍,对今后类似工程的设计与施工具有很好的参考借鉴价值。

关键词:取水口;围堰;深层搅拌桩;防渗处理;压密灌浆

Water Levee gravity pipe to the technical requirements of the seepage control construction

Li ChuanMing, nie jie, Wang Ju

Abstract: Ying River water intake works cofferdam inside and outside the water level difference is greater than 8.0m, rarely encountered in hydraulic engineering construction in the city, but also across the flood season of construction, the construction conditions are very bad; using the Levee gravity pipe impermeable cutoff walland compaction grouting a combination of measures to achieve the expected treatment effect. The reference value is a good reference on the design and construction of similar projects in the future through the introduction of the engineering technical disclosure.

Keywords: water intake; cofferdam; deep mixing piles; seepage control; compaction grouting

1.引言

根据水利部淮河水利委员会主持的《阜阳华润电力有限公司(2×600MW)超临界燃煤发电机组工程颍河取水口及引水管、颍河灰管桥洪水影响评价报告》专家评审会上形成的专家评审意见,受阜阳华润电力有限公司的委托,我院对颍河取水口及取水穿堤自流管工程进行设计,现对取水口围堰及穿堤自流管防渗处理施工的设计技术交底作如下简叙。

2. 围堰工程

(1)鉴于本工程施工时间紧迫,必须在临近汛期时施工,围堰挡水位较高(内外水位差>8.0m),在本市水利工程建设中很少遇到挡如此高的水位,且颍河水位上涨较快,因此施工条件十分恶劣。本工程施工成败的关键就在于围堰工程,因此,围堰的施工与监理单位一定要选择具有相应资质的相应队伍承担。

(2)围堰属临时性建筑物,其设计由施工单位自行负责。施工单位必须认真进行本流域的水文、气象分析,尤其是围堰挡水期间颍河的水位、降雨量、水情数据的分析,精心设计,务必注意围堰的抗滑、防渗、防冲等问题,以保证工程的施工安全。……