基于钻孔灌注桩施工事故原因分析及质量保证
2016-05-14冯志刚
冯志刚
【摘要】钻孔灌注桩在各类土木工程中广泛应用,具有抗震性好、承载力大、施工噪音小、可以解决特殊地基沉载力等诸多优点。目前在国内公路桥梁基础工程领域中钻孔灌注桩基础已占据了重要地位,但灌注桩地下施工不可预计因素多,工程质量较难控制,桩基施工既有机械操作,又有钢筋加工、混凝土拌制和灌注等多种工作,工序种类繁多,影响因素多,水下混凝土施工要求严格,稍有不慎,就可能出现孔底沉泥、缩颈、夹渣、断桩等,可能造成质量事故,因此,施工中必须严格监管质量。
【关键词】钻孔灌注桩;施工事故
【Abstract】Bored widely used in all types of civil engineering, has good shock resistance, large capacity, small construction noise can be solved special forces Shim Foundation and many other advantages. Currently drilling in the domestic highway bridge infrastructure projects in the field of pile foundation has occupied an important position, but underground construction pile unpredictable factors, difficult to control the quality of the project, both the pile foundation construction machinery operation, there are steel processing, concrete mixing and perfusion and other work processes a wide range of factors and more demanding underwater concrete construction, the slightest mistake, it may appear hole bottom silt, necking, slag, broken pile, may result in quality accidents, therefore, must be strict supervision of construction quality.
【Key words】Bored;Construction Accident
质量控制的定义是:质量管理的一部分,致力于满足质量要求。钻孔灌注桩施工的质量控制,是指为保证工程合同规定的质量标准对钻孔灌注桩施工进行的质量控制。由于施工阶段是使业主及工程设计意图最终实现并形成工程实物的阶段,也是最终形成工程实物质量的系统过程,所以施工阶段的质量控制也是一个经由对投入的资源和条件的质量控制(事前控制)进而对生产过程及各环节质量进行控制(事中控制),直到对所完成的工程产出品的质量检验与控制(事后控制)为止的全过程的系统控制过程。本文从工程施工角度,对钻孔灌注桩施工的三个阶段质量控制进行分析和讨论。
1. 钻孔过程中出现的问题及原因分析
1.1偏斜孔。由于钻机在安装时没有支撑好、以及桩孔地质构造不均匀等原因,从而引起钻机整体或钻头在钻孔过程中发生偏斜,导致出现偏斜孔。……