预防性维护与备件管理联合数学优化研究
2015-05-22郑军辉张永军赵兴兵
郑军辉?张永军?赵兴兵
摘 要:预防性维修需要一定数量备件库存。若库存备件数少于预防性维修周期内所需备件数,那么在缺失备件到货前,待修系统将经历非必要停机,生产遭受非必要损失。另外,若库存备件数量大于预防性维修周期内所需备件数量,会导致非必要的备件库存费用。理想状态是库存备件数量恰等于预防性维修周期内所需备件数。然而,故障(维修)次数是一个随机变量,使得确定备件确切数量变得困难。本文在前辈所建模型的基础上,利用更新函数以及数学分析手段,讨论如何确定预防维修周期初始,最优库存备件数量,继而使得整个周期内总费用最小;并对基于最小停产损失的预防性维护体系优化模型进行研究。
关键词:预防性维护;备件管理;联合优化;可靠性优化
Abstract: Preventive maintenance needs a certain amount of spare parts inventory. If the spare parts inventory less than the preventive maintenance cycle required, so before the unavailable items arrival, the system will undergo unnecessary downtime, bring unnecessary production losses. In addition, if the spare parts inventory is greater than the preventive maintenance cycle required, will lead to unnecessary spare parts inventory costs. Spare parts inventory quantity equaling to the required amount of spare parts in the preventive maintenance cycle is ideal. However, fault (maintenance) is a random variable; make it difficult to determine the exact amount of spare parts. In this paper, on the basis of predecessors and the existing model, using the update function and mathematical analysis method, study how to determine the optimal amount of spare parts inventory at the start of preventive maintenance period, then get the whole cycle minimum total cost. And research the optimization model of the minimum loss preventive maintenance system.
Key Words: Preventive Maintenance, Spare-parts Management, Joint Optimization, Reliability Optimization
1 引言
库存管理作为一项重要研究内容,把它和维护策略相联合研究已经受到国际维护领域极大关注,单从21世纪初的五年中,接连有十余篇国际著名期刊(例如 IEEE Transactions,IIE Transactions等)报道学者们的研究成果。联合研究首先可以得到全局最优,而不像局部最优。另外,研究表明,联合研究往往会较大地节约成本,减少费用。
2003年,Brezavscek & Hudoklin[1]建立了库存备件和设备零件批量更换联合优化策略之解析形式数学模型,其中决策变量为成批更换周期和最大库存量。该模型将订货提前期固定,对周期维护和库存备件联合优化问题进行了深入研究,给出了联合模型的解析形式,提供了一个解决维护联合优化问题的新途径,并将研究成果成功应用于欧洲电气火车部件维护和库存联合管理上。……