天然气管道工程的水土保持及防治措施
2015-04-13冯敏
冯敏
摘 要:该文以黔江-酉阳-秀山天然气管道工程水土保持方案为实例,结合渝东南地区植被、地形、土壤侵蚀等特点,介绍了天然气管道工程水土保持防治措施。
关键词:管道工程;水土保持;防治措施
中图分类号 TU688 文献标识码 A 文章编号 1007-7731(2015)06-101-02
Water-soil Conservation and Prevention Measures of Natural Gas Pipeline Project
Feng Min
(Chongqing Jingjia Engineering Design Consultation Co., Ltd., Chongqing 400041,China)
Abstract:The author takes the water-soil conservation plan in Qianjiang-Youyang-Xiushan Natural Gas Pipeline Project as an example and combines the characteristics of the vegetation,terrain and soil erosion in the southeast area of Chongqing to carry out a brief discussion about the water-soil conservation measures in such projects as well as the sustainable development of regional economy and landscaping.
Key words:Pipeline project;Soil and water conservation;Control measures
1 工程概况及水土保持
黔江-酉阳-秀山天然气管道工程位于重庆市,工程跨黔江、酉阳和秀山3个区县。工程干线起点为黔江首站,向南敷设,到达青塘村分输阀室,最后进入秀山末站。支线起点从青塘村分输阀室向南敷设,穿越G319和G65包茂高速后到达酉阳站场。输气干线管道长度约190.9km,支线管道长度为7.2km,沿线改扩建3座站场,新建7座普通线路截断阀室,1座分输阀室,管道系统设计输气量规模为49×104m3/d。
该工程占地总面积为79.56hm2,土石方开挖和回填量为25.46万m3,工程区原地貌土壤平均侵蚀模数为2 422.2t/(km2·a),为轻度侵蚀,工程扰动地表后可能造成的水土流失总量为17 991.0t。根据工程的布局与施工特点进行两级防治分区,一级分区为天然气站场和中间阀室防治分区和管道工程防治分区,其中管道工程防治分区的二级分区为管道作业带防治亚区、河流穿越防治亚区、铁路道路穿越防治亚区。水土保持工程主要包括2个部分,一是主体工程已列的恢复排水沟,恢复土地埂坎,挡土埂等措施,二是在建设过程中新增的水土保持措施,新增的措施主要有:剥离表土、土地整治、框格植草护坡、浆砌块石挡墙、撒播草籽、种植灌木、临时拦挡、排水沟、沉砂池、围堰拆除、临时覆盖等。……