预应力钢筋砼密肋空心叠合箱梁的研究
2012-04-23邝思芹史瑞凌郭琼华杜慧宇
邝思芹 史瑞凌 郭琼华 杜慧宇
摘要:针对常用的先简支后连续梁桥的施工不足,本文提出了一种新型的梁桥转换结构,即预应力钢筋砼密肋空心叠合箱梁的结构形式,并提出了预应力钢筋砼密肋空心叠合箱梁的结构两阶段计算方法及注意事项。该结构具有自重轻,结构受力合理,施工方便,整体性好,总体造价低等优点。
关键词:预应力钢筋砼箱梁;密肋板,空心叠合梁;现浇装配整体式结构;特点和优势;
Abstract: The first simply supported continuous beam bridge construction, the paper proposes a new girder bridge converter structure that the prestressed reinforced concrete ribbed hollow the superimposed box girder structure in the form, and prestressed reinforcement the two-stage concrete ribbed hollow the superimposed box girder structure calculation methods and precautions. The structure has a light weight, force structure, convenient construction, good integrity, low overall cost.Key words: prestressed reinforced concrete box girder; ribbed plate, hollow composite beam; cast-in-place prefabricated structure; characteristics and advantages;
中图分类号:TU45 文献标识码: A文章编号:2095-2104(2012)01-0020-02
0概述
随着梁桥的发展,一种兼顾简支梁桥和连续梁桥优点的桥型,既先简支后连续梁桥应运而生。先简支后连续预应力混凝土梁采用了先按简支梁规模化预制,再现浇梁间湿接缝、张拉负弯矩预应力束进行体系转换,最后进行桥面铺装的施工工艺,比满堂支架、悬臂浇筑等其他施工方法要简单方便;同时预制梁的施工质量也有保证,行车平稳,刚度大,结构受力合理,因而广泛应用于高等级公路。
目前,常用的先简支后连续梁桥的施工工艺是:
(1)、按照后张法预应力砼施工工艺预制T梁,吊装T梁的时候,设置临时支座,按简支梁安装方法安装就位,并在连续墩上设置永久盆式支座。
(2)、待一联吊装完毕后,进行墩顶两侧第2道横隔板之间的横隔板、湿接缝和接头的施工,并设置二期预应力束。
(3)、接缝混凝土强度达到设计要求时,进行联系端第二期预应力束的张拉和灌浆。
(4)、灌浆强度达到要求后,逐步均匀卸落临时支座,使盆式支座受力,完成简支梁转换成连续梁。……