浅谈海上潮间带风电场无过渡段单管桩基础施工方案
2012-04-23王徽华曹春潼冯小星
王徽华 曹春潼 冯小星
摘要:根据国外经验海上风电场基础适合采用大直径钢管单桩结构,目前国内尚处于探索试验阶段,其难点是施工效率的低、垂直度难以控制。我司通过1年多的探索和试验,成功掌握一套海上潮间带风电场无过渡段单管桩基础施工方法,该套施工方法可达1根/天的单管桩施工效率,垂直度均小于2.75‰,远小于国际上的5‰。适合于海上潮间带风电场规模化推广应用。
关键词:海上风电场、潮间带、单管桩、液压冲击沉桩、施工工艺
Abstract: based on the foreign experience offshore wind farms for the foundation of large diameter steel pipe single pile structure at present, our country is still in exploring stage, it is difficult to test the construction efficiency is low, the vertical degree is difficult to control. Our company through more than a year of exploration and test, the success to master a set of offshore wind farms intertidal zone without transition period of single pile foundation construction method, this set of construction method can reach 1 root/day of single pile construction efficiency, vertical degree are all smaller than 2.75 ‰, far less than the international 5 ‰. Suitable for sea on intertidal wind farm scale application.
Keywords: offshore wind farms, intertidal zone, single pile, hydraulic impact piles, construction technology
中图分类号: TU473.1 文献标识码: A 文章编号:
引言
随着化石能源逐渐枯竭,国际逐渐加大对非化石能源的开发和生产。近几年国内对非化石能源的开发主要致力于风力发电。由于陆上风电资源主要分布于西北、东北等远离人口密集的偏远地区,且陆上风电存在弃风、远距离输送、环境影响等因素,而国内人口密集的发达城市基本位于沿海地区,沿海海域风力发电开发利用前景广阔。
目前国内海上风电场尚未大面积开发利用的主要原因是施工设备短缺、施工技术不成熟等导致施工效率低下、施工成本高。鉴于当前国内的形势,我司定制了一艘可坐滩(搁浅)作业、有双层液压抱桩器、360°全回转双钩起重量800T的多功能施工船,并采购了一套荷兰IHC-S800液压打桩锤。利用这些主要设备和社会上的辅助船机设备,我司通过1年的实践摸索,探讨出一套高效率、低成本的潮间带无过渡段单管桩施工方法。
工程概述……p>