大跨度连续刚构的0#块施工
2012-04-10李小鹏陈睿文登国
李小鹏 陈睿 文登国
摘要: 连续刚构桥作为一种经济节约、施工简便的桥型在桥梁界广为采用。本文结合主跨216m的金塘大桥东通航孔桥的施工过程,全面阐述了其0#块的托架、模板设计以及钢筋、混凝土和预应力施工,为其他类似大跨度桥梁0#块的施工提供借鉴和参考。
关键词: 大跨度连续刚构;0#块施工
Abstract: as a kind of economic continuous rigid frame bridge of saving, construction simple in the bridge world widely. Based on the main 216 m jintang bridge! The construction process of east navigation, the article expounds its blocks 0 # bracket, template design and reinforced, concrete and prestressed construction, for other similar large span bridge blocks 0 # of construction to provide the reference and reference.
Keywords: of long span continuous rigid frame; 0 # blocks construction
中图分类号:TU393.3文献标识码:A 文章编号:
一、工程概述
东通航孔桥(K29+955~K30+415m、B1~B4墩)全长460m,桥型为122+216+122m连续刚构,上部采用分幅断面单箱单室变高度三向预应力混凝土箱梁结构。
图1 东通航孔桥桥型布置图
主墩编号为B2(K30+077)和B3(K30+293),其墩顶0号梁段单幅为单室直腹板箱梁,采用纵、横、竖三向预应力。箱梁顶板宽12.3m,厚50cm。底板宽6.3m,厚130cm。两翼悬臂长3.0m,箱梁腹板厚80cm,梁高13.3m,桥面设置2%的向外侧单向横坡。主墩墩顶设有薄横隔板4道,与主墩薄壁墩身厚度对应。0号梁段砼为C55海工混凝土。0号梁段砼分两次浇筑,首次砼连同墩身切角下1m长度范围一起浇筑至标高+34.223m,第二次浇筑剩余7.7m高混凝土。
二、总体施工布置及施工流程
0号梁段采用墩身预埋贝雷托架施工,0号梁段砼分两次浇筑,首次砼连同墩身切角下1m长度范围一起浇筑至标高+34.223m,第二次浇筑剩余7.7m高混凝土。起重设备为315塔吊,砼通过泵机输送至浇注点。体外横隔板最后浇注。由于在两幅桥中间安装塔吊,在施工0#块箱梁翼板时,预留塔吊位置,待塔吊拆除后,布置钢筋及预应力后再进行浇筑砼。
施工流程如下:
图2 东通航孔桥0#块总体施工流程图
三、0#块托架及模板的设计与施工……p>