建筑工程中预应力管桩的施工技术与质量控制管理措施

2012-04-10刘思

城市建设理论研究 2012年6期
关键词:承载力质量施工

刘思

摘要:预应力管桩以其对地质条件适应性强、承载力高、单位承载力造价低、施工速度快、工期短、监理难度小、检测方便等特点而被广泛运用于基础工程中。本文主要结合相关的施工工程资料,对建筑工程中预应力管桩的施工技术与质量控制管理措施作了探讨和阐述。

关键词:建筑工程预应力管桩施工技术质量控制管理

Abstract: the prestressed pipe pile geological conditions good adaptability and high bearing capacity, unit bearing capacity low cost, construction speed is quick, short construction period and the difficulty of small, supervision inspection is convenient wait for a characteristic and is widely used in basic engineering. This paper mainly related with the combination of construction engineering material, to building engineering construction of prestressed pipe pile technology and quality control measures were discussed and described.

Keywords: building engineering prestressed pipe pile construction quality control management technology

中图分类号:O213.1 文献标识码:A文章编号:

1施工准备

1.1技术准备

1.1.1组织测量人员加密导线控制点和水准点,建立施工控制网,做好工程定位放样,并请监理、业主、设计单位有关人员核验,办理好技术复核手续。

1.1.2根根据地质报告计算该工程的典型桩的理论压桩阻力,绘制压桩阻力曲线,对最大压计阻力有充分的估计,以便争取有效施工措施减少压阻力,使施工顺利进行。

1.1.3仔细审核施工图,对图纸存在的疑问及时请业主和设计方予以解释说明;

1.1.4以施工图为依据编制桩位编号图,并根据施工图放样桩位,用合适的竹签打入地面标记桩位,桩位允许偏差≤5cm;周围撒上Φ500mm圆形白灰线,以便压桩前查找和桩机行走到位。

1.1.5桩位放样和复核前均请监理人员监督复核验收,压桩前施工人员和桩机指挥员必须对桩位逐个复核,及时校正并采取不定期复查基准轴线和三复核的方式(压桩前复核、压桩时复核,压桩后复核)。

1.2现场准备

1.2.1试桩地点选在DK147+387.1左侧,具体试桩桩位见“试桩桩位示意图”。因为该地段预应力管桩加固深度较深(39m),具有代表性,且该段场地已经用碎石处理过,场地平整,承载力较好,有利静力压桩机行走。……