预应力连续箱梁挂篮施工技术探索
2012-04-10曾小云
曾小云
摘要: 本文结合某预应力箱梁施工实例,主桥箱梁除墩顶块件外,各单“T”箱梁均采用挂篮悬臂浇筑法施
工;提出了桥梁中挂篮安装,同时对挂篮如何在桥梁中实现逐段浇筑施工进行探讨,为同类工程挂篮施工提供借鉴。
关 键 词:梁箱施工挂篮施工悬臂现浇挂篮安装
中图分类号:TU394文献标识码:A 文章编号:
Abstract:This combination of a prestressed box girder of main bridge box beam construction examples,
except the pier top block pieces, the single" T" box Liang Jun by suspension-basket
cantilever pouring construction; proposed the bridge hanging basket in installation, the
hanging basket in realizing how bridge casted in segment construction carries on the
discussion, for similar construction hanging basket construction to provide reference.
Key Words: Box girder construction;Hanging basket construction;Cast in place cantilever ;
Hanging basket installation
1工程概况
本项目广梧高速第十八合同段路线全长14.833km,其中封开西江特大桥桥梁孔跨布置为:6×30+8×40+(66+120+2×138+120+66)+4×30+3×30m,主桥上部结构采用(66+120+2×138+120+66)m刚构-连续预应力砼连续梁,下部结构为单薄壁空心墩;引桥为预制预应力砼先简支后连续刚构T梁,下部结构为独柱T型薄壁墩;桩基均为钻孔灌注桩。主桥箱梁除墩顶块件外,各单“T”箱梁均采用挂篮悬臂浇筑法施工。
2挂篮安装
挂篮是梁体悬臂浇筑专用设施,既是施工梁段的承重结构,又是施工梁段的作业现场,本工程采用菱形挂篮施工。为了有效地确保悬臂浇筑施工技术,挂篮安装施工质量起着相当关键作用,必须对挂篮的安装的每个环节进行细化施工。
2.1挂篮系统安装
(1)承重系统。主桁承重系统由主桁架、前上横梁及前、后下横梁组成。主桁架采用16Mn钢板加工而成,断面为250mm×250mm,各杆件之间用连接板销接。前、后上横梁采用[20、[16及钢板连接板连接而成,除吊杆连接板为16Mn外,其余材料均为Q235。前、后下横梁均用16Mn钢板焊接而成,断面为230mm×500mm,顶板均采用22mm厚的钢板,侧墙采用12mm的钢板。
(2)提升系统。提升系统主要受力吊杆采用16Mn钢板和φ32精扎螺纹钢吊杆,其余部分均采用φ32精扎螺纹钢,为了加强挂篮的通用性,吊带分别采用1m、2m两种规格,全部采用钢销连接。……