220kV全室内变电站建设要点分析
2012-03-23黄伟崔晓苗
黄伟 崔晓苗
中图分类号:TM411+.4文献标识码:A 文章编号:
摘要:随着经济的高速发展,城市化进程明显加快,中心城区土地资源日趋紧缺,在城市中心的工业用地面积日益减少,郑州腾飞220kV变电站(融城变)地处郑州CBD,第一期主变规模2×180MVA、220kV出线2回、110kV出线4回、10kV出线16回,全部等级出线都为电缆出线,无架空线。变电站周围人口密集高档社区林立,而全室内型变电站正好具备“环境有好、资源节约”的技术特点,符合城市建设需要。
Abstract: with the high speed development of economy, obviously faster urbanization, the city centre land resource is in short supply, in the city center of industrial land area is decreasing, zhengzhou 220 kV substations off (the city into change) is located in zhengzhou CBD, first phase of the main transformer scale 2 x 180 MVA, 220 kV, 110 kV qualification 2 to 4, 10 kV to qualify to qualify and back, all levels qualify for cable outlet, no aerial. Around the transformer substation populated with high-grade community, and the whole indoor substations with just type "environment have good, conservation of resources" of the technical characteristics, conform to the city construction need.
一、室内变电站技术特点土建与电气配合问题
中心城区的全室内变电站,为了减少对周围环境的影响,大多采用室内紧凑型GIS(全封闭组合电气)以及电缆线路的出进线。并联式电抗器、电容器主变等设备均布置在室内,全室内变电站土建施工和电气施工的交叉点较多,应充分考虑土建专业和电气专业的配合问题。特别是土建设计应充分考虑到,电气设备的尺寸及运输路径问题,设备就位须经过的门框尺寸应略大于设备尺寸。 分布在一层以上的重型电气设备,应充分考虑土建结构主次梁承重重量和分布位置以及安装中的运输途径问题,如设备吊装平台与设备就位位置距离较远且室内无行吊,就给设备就位造成很大的困难。
主变压器上部出线套管用SF6气体绝缘金属套管与GIS设备连接,设备对接的误差范围较小,对设备就位精度和土建预留洞口标高和水平位置提出了较高的要求,主变上部的套管吊装主要依靠土建预埋吊钩,吊钩位置应符合设备吊装力学特性,且倒链吊装高度空间应满足施工要求。……