钦寸水库输水隧洞工程施工通风浅析

2012-03-23姜海华钱林波何迪锋

城市建设理论研究 2012年4期

姜海华 钱林波 何迪锋

摘要:根据钦寸水库输水隧洞工程的特点和隧洞施工设计方案,对掘进机施工通风的独头通风长度、施工通风模式、系统参数、机械选型、通风布置等进行了初步分析,指出:隧洞宜采用混合式通风方案;风机最大送风长度为4000m,通风管平均百米漏风率为2%;风机应选用高效、低噪音的轴流式风机,风管应选漏风率低、耐久性强、安装方便的大直径软管。

关键词:引水隧洞;通风方式;风机;钦寸水库工程

中图分类号: TU834.3 文献标识码:A文章编号:

Abstract: according to the imperial inch reservoir water the characteristics of tunnel engineering and design scheme tunnel construction, the construction of TBMS ventilation alone ventilation length, head of construction ventilation mode, system parameters, equipment selection, ventilation and arrangement of the paper points out that: tunnel appropriate USES hybrid ventilation plan; The biggest fan air supply length of 4000 m, the average meters ventilation air leakage rate is 2%; Fan should choose high efficiency, low noise of axial flow fan, duct air leakage rate is low, the durability rappel/abseil stations should be strong, easy installation of large diameter hoses.

Keywords: diversion tunnel; Ventilation mode; Fan; Qin inch reservoir project

1工程概述

钦寸水库输水隧洞工程从钦寸水库向宁波(亭下水库)输水,采用有压输水方式,输水隧洞从钦寸水库右坝头上游约300m处进水口起,经石沿山、张家车、晚香岭、倪家岙等处一直通向亭下水库管理区出口和亭下水库出口,全长为29112.00m。

钦寸水库输水隧洞工程存在着隧洞埋深大、洞线长、施工条件复杂和倒洞型支洞施工困难等特点,使得长隧洞施工通風技术变得复杂,通风系统设计将直接影响隧洞的独头掘进规模、工程工期和工程投资等。因此,必须对长隧洞施工通风进行研究,以适应快速掘进的施工需要。

根据工程地质、环境气候和隧洞施工的特点,隧洞施工采用以钻爆法的施工方案。钻爆施工工作面共计11个,独头施工最大长度为3.74km,施工支洞4条。施工通风方式选择根据长隧洞工程施工技术和经验,一般采用机械通风,基本形式为压入式、抽出式(压出式)、混合式和巷道式等。需结合隧洞施工特点和各种通风方式的使用条件等进行研究,选择技术上先进、经济上合理、安全有保障的通风方式。……