悬浇连续梁合拢段施工技术探讨
2012-03-23周戈
周戈
[摘要] :现浇悬臂施工预应力混凝土连续梁的合拢是连续梁施工中的关键工序,合拢工序不同,将会在结构中产生不同的最终恒载内力: 因此有必要介绍现浇悬臂施工预应力混凝土连续梁的合拢程序及技术措施,本文在分析了合拢段施工的施工难点及其关键施工技术等方面,简单地探讨了悬臂浇筑连续梁合拢工艺和施工技术。
[关键词]:连续梁;合拢段;施工技术;
[Abstract] : Cast-in-place cantilever construction of prestressed concrete continuous beam strengthening of the continuous girder is in the construction of the key working procedure, fold process is different, will be in the structure of the constant load eventually produce different internal force: so it is necessary to introduce cantilever construction of cast-in-situ prestressed concrete continuous beam strengthening of program and technical measures, this paper analyzes the construction period of the folded construction difficulties and its key construction technology and so on, simply discusses the cantilever continuous beam technology and construction technology folded.
[Key Words]: Continuous beam; Fold section; Construction technology
中图分类号:TU74 文献标识码:A 文章编号
引言
随着建筑材料与预应力技术的进步,以及日益完善的设计理论和计算机技术的发展,预应力混凝土连续梁具有容易达到与周围环境相协调的简洁而美观的形式、保证施工期间桥下通航、通车运营未受影响的显著优点,从而被广泛应用。 平衡悬臂浇筑法是我国大跨度预应力混凝土连续梁施工的主要方法之一, 梁体从桥墩上平衡向两边悬臂现浇伸出。合拢段施工成为连续梁施工和体系转换的重要环节,能保证结构的受力和线形满足设计要求。
1 合拢段施工顺序
不同的橋梁合拢段施工顺序,将引起不同的施工内力,甚至结构内力再分配效应。因此,影响结构的恒载内力分布是否合理,主要看桥梁合拢段施工顺序的是否适当。另外,施施工单位根据合拢段施工的施工组织安排,以满足各墩相应的匹配进度。再者,桥梁的设计和现场施工的具体情况有不可避免的有一些差距,到了合拢施工阶段,这种差距累积是相当大的,这些问题都需要在合拢段的施工中得到适当地解决。……