高寒深水地区双壁钢围堰拆除施工技术

2012-03-23吕鹏涛

城市建设理论研究 2012年4期
关键词:施工

吕鹏涛

摘要:以兰渝铁路(兰州枢纽)杨家湾黄河特大桥5号墩承台为例,详细介绍,高寒深水地区双壁钢围堰拆除施工技术,本工程具有高寒、深水、流动河水、水下作业的技术难点,工程实践证明此项技术效果良好,施工技术可行,可为今后类似工程的施工提供技术借鉴。

关键字:高寒深水双壁钢围堰拆除施工技术

Abstract: the LanYu railway (lanzhou hub) YangGuWan Yellow River big bridge 5 # pier elevated pile caps as examples, the paper introduces, alpine deep water double-wall steel cofferdams of the demolition in the construction technology, the project has the alpine, deep water, the river flow, underwater operations technical difficulties, and engineering practice shows the technology to good effect, construction technology and feasible, and can be for the other similar project construction to provide the technology reference.

Key word: alpine deep water double-wall steel cofferdams of the demolition construction technology

中图分类号:TU74文献标识码:A 文章编号:

工程概况

杨家湾黄河特大桥位于兰州市东岗镇,桥梁全长1442.13m,双线货运铁路桥,设计43个墩台,为保证通航要求, 跨越黄河的3、4、5、6、7号墩梁体设计为(40m+64m+64m+40m)预应力变截面连续梁,其中5号墩处于河道中央,水深7m,水流湍急,黄河汛期对桥梁施工影响较大,径流量主要源于上游流域的降水和冰雪融水,年径流量随降雨和气温的变化而异,桥址有冬天寒冷的特点,黄河河水兰州段枯水期为每年的1月至3月,此时径流量小,但气温处于全年最低,水面气温平均零下15℃。该处地质卵石覆盖厚度2m,其下为花岗岩。5号墩承台施工采用双壁钢围堰,目前桥梁施工完毕,按黄河管理委员会要求对双壁钢围堰进行拆除,恢复原有河道,满足通航要求,

2、双壁钢围堰的拆除

2.1双壁钢围堰组成结构

图一:双壁钢围堰组成结构

如图一所示:双壁钢围堰为内径19m,外径20.4m的圆柱形钢结构容器,围堰由水平桁架、竖直桁架和内壁、外壁钢板组合而成,水平桁架由内壁加强环形角钢、外壁加强环形角钢、水平桁架斜杆角钢组成,竖直桁架由竖直桁架……

登录APP查看全文

猜你喜欢

施工
后浇带施工技术在房建施工中的运用
铝模板在高层建筑施工中的应用
后浇带施工技术在房建施工中的践行探索
新型环保建筑材料在土木工程施工中的应用
防渗漏技术在民用建筑施工中的应用
后浇带施工技术在房建施工中的应用
后浇带施工技术在房建施工中的应用
土木工程施工技术创新探讨
防渗漏施工技术在房建施工中的应用
土木工程施工实习的探讨与实践