基坑工程勘查抽水试验探讨
2012-03-23李强
李强
摘要:在基坑工程勘查过程中进行抽水试验的主要目的是为了确定含水层的水文地质参数,包括给水度、贮水系数、渗透系统以及导水系数,确定出抽水井的单位涌水量,在单井停止抽水时,分析观测井水位与时间曲线的关系,最终确定出单井抽水的影响半径以及干扰井群的抽水流量、漏斗形态与降深等指标。本文针对某基坑工程勘查过程中的抽水试验进行分析,希望能够对类似工程起到借鉴作用。
关键词:基坑工程;勘查;抽水试验
Abstract: in the foundation pit engineering exploration process of pumping test the main purpose is to determine the aquifer hydrogeologic parameters, including water supply, water storage tank of coefficient, osmosis system and the water coefficient, confirmed the pumping Wells yield unit, in the single well stop pumping, analyzes observed a time of curve and well water relations, and finally confirmed the single well pumping radius and interference of pumping Wells of flow, funnel form and drop depth of the index. In this paper a foundation pit engineering exploration pumping test in the process of analysis, the hope can be used for reference for similar engineering.
Keywords: foundation pit engineering; Exploration; Pumping test
中图分类号:O212.6文献标识码:A 文章编号:
一、抽水试验的具体步骤
(一)准备工作
进行抽水试验的仪器设备主要有抽水设备、流量计、温度计以及水位计等。抽水设备一般是水泵或者空压机,而水位计则为测钟、浮子式自动水位仪以及电测水位计等;在选择流量计时要按照预计水量、现场条件来进行,比较常用的流量计包括矩形堰、量筒、孔板流量计以及流量箱、三角堰等;水温计通常选择温度表、水温仪等。
(二)成孔
可以在勘察钻孔的同时进行抽水试验抽水孔与观测孔的成孔,通常抽水孔要选择最佳抽水试验部位的勘察孔,根据具体抽水试验要求的孔径与孔深进行施工,并且成孔的垂直度要特别注意严加控制;通常在垂直于地下水流向的方向上布置观测孔,根据含水层的厚度、影响半径以及降深来确定它与抽水孔的距离。如果在野外环境中施工,出于方便考虑,抽水孔可以用150mm的钻头成孔,钻至设计深度后再下入146mm的套管;……