浅谈某滩涂作业清障船冷却水系统设计
2025-07-28朱小艳刘亚马玲刘迪潘均发
中图分类号: U664.81+4 文献标志码:A
Design of Cooling Water System for an Intertidal Obstacle Removal Vessel
HUANG Haibin', WU Darong², CHEN Jian1, WU Dong', WANG Ning³ (1.GuangzhouMarineEngineringCorporation,Guangzhou51025o,China;2.AfaiSouthem Shipyard (PanyuGuangzhou)Ltd, Guangzhou51431,China;3.LiuzhouYufengDistrictAzureTechnologyPromotionServiceStudio,Liuzhou54506,China)
Abstract: The primary challenge for vessels operating in intertidal zones is cooling water system clogging, which impedes prolonged continuous operation. Particularly during beaching conditions,ensuring reliable domestic power supply becomes critical.Taking an intertidal obstacle removal vessel as an example,this paper outlines its cooling water system design, including sea chest arangement and strainer optimization methods.Solutions for maintaining power supply during beaching operations are presented, ofering references for similar vessel designs.
Key words: obstacle removal vessel; intertidal operations; vessel beaching; cooling water system
1 引言
滩涂作业船舶需在极浅水域航行,其在推进器作用下易使海床泥沙泛起,进入船舶冷却水系统产生堵塞,导致无法长时间连续作业。另外,随着海水的潮涨潮落,难免会频繁地引起船舶坐滩现象,为此需考虑解决滩涂作业时冷却系统受淤泥、杂物堵塞问题,以及船舶坐滩时船舶生活用电,满足船上人员的正常生活需要。但船舶坐滩时往往无法连接岸电,需船舶自身供电,而其关键点是解决坐滩时发电机的冷却问题。因此其冷却系统设计方案的可行性将是滩涂作业船舶的重点和难点,需要基于其特殊性,有针对性提出解决方案,保证船舶在所要求的特殊工况下正常工作。本文以 30m 清障工程船为例,简要介绍该型船动力系统冷却设计方案。
2 船舶概况
本清障工程船主要功能是执法清理滩涂定置网。
本船为双机、双桨、双舵、通长甲板排水型船,全船为钢质焊接结构。船长约 30m ,满载排水量约260t ,设计吃水约 1.1m ,满载巡航速度约 8kn ,续航力 600nmile ,自持力3昼夜,航速约 10kn ,主机功率447kW×2 台,发电机组功率 100kW×2 台。

3 冷却水系统设计
滩涂作业船舶的冷却水系统设计是保障清障工程船在滩涂区域长期工作的关键,其主要与海底门布置、冷却系统海水滤器设计及供发电机组冷却水系统设计相关联。本文将对此进行扼要介绍。
3.1机舱海底门布置方案
通常,机舱海底门布置位置有以下几种常见型式:1)两舷各设置高低位海底门;……