内港池码头大型钢梁整体发运研究与实践探索
2025-07-13战丽娜
【中图分类号】:U445 【文献标志码】:A 【文章编号】:1008-3197(2025)03-01-04
【DOI编码】:10.3969/j.issn.1008-3197.2025.03.001
Research on the Overall Shipping of Large Steel Beams at Inner Basin Wharf
ZHAN Lina
(China Railway Construction Bridge Engineering Bureau Group Fourth Engineering Co.Ltd.,Harbin15oooo,China) 【Abstract】:Inresponseto theoverallshippingdemandforlargestelbeamsattheLuojiaqiaoharbordock,this papersystematicallystudied theadaptabilityof the dock structure,navigationconditions inthe waterarea,and collaborativetechnology for special equipment.Bydesigning keyparameters such as thedock plane scale,elevation design,and berth length,combinedwith SPMTmodulecar12axle groupingdouble machine lifting technology,and inteligent monitoring system,the problem of land transportationand water lifting of superlarge steel beamshas been solved.The results showed that through collaborative optimization of \"harbor pool equipment steel beam\",the shipping efficiency increased by 60% and the safety accident rate decreased by 65% :
【Key words】: girder steel;inner harbor basin wharf; large steel beams;overallshipping
在现代桥梁建设中,大型钢梁作为关键部件,发运环节直接关系到桥梁工程进度、质量与成本。随着桥梁建设规模扩大及技术水平提高,大型钢梁的尺寸和重量不断增加,对发运技术和管理提出了更为严峻的挑战]。工厂内加工制造可以保证钢梁的制造精度,梁段整体发运至桥位可以加快桥梁节段拼装环节,进度减小施工组织难度2。但是工厂制造的整体钢梁因重量和体积大,陆地车辆很难运输;海运方案虽更为便捷,但对存储、装运条件也提出了更高要求3]。
罗家桥港码头地处长江 12.5m 深水航道核心区段,距长江入海口约 138.9km(75 海里),依托毗邻的靖江重工钢结构制造基地,承担着区域内多座跨江桥梁的钢箱梁发运任务,形成了“工厂加工一码头装运一水上运输\"的全产业链一体化作业模式。本文针对大节段钢箱梁运输中面临的码头结构适配性不足、水域通航风险高、特种装备协同效率低等技术难点展开系统性研究。
1吊装大型钢梁码头技术要求
1.1码头平面尺寸
码头平面尺寸是确保大型钢梁顺利发运的基础条件,其合理性直接关系到船舶停靠、钢梁装卸及运输车辆通行等关键环节的效率与安全。
码头采用岸壁式地下连续墙结构,根据水工结构力学及装卸工艺需求耦合设计,确定前方作业带关键尺寸。前方胸墙至锚碇墙中心的基础间距要满足结构抗倾稳定性要求,同时为自走式模块化平板车(简称\"SPMT模块车”提供充足的转向空间与荷载分布区域。……