四机抬吊在景观桥吊装中的应用

2021-08-09杨弟相

关键词:施工

杨弟相

【摘  要】通过工程项目实例,论文详细阐述了4台起重机抬吊的验算及操作全过程,在工期紧张及现场施工场地受限不能满足超大吨位吊车施工时,采用4机抬吊对安全、质量、进度、经济效益有很好的保证。该项目实例对多机抬吊在施工中的应用有着较好的借鉴意义。

【Abstract】Through the project example, the paper elaborates the checking calculation and operation process of the lifting of 4 cranes. When the construction period is tight and the site construction site is limited, it can not meet the requirements of the construction of the large tonnage crane, the use of four cranes can ensure the safety, quality, progress and economic benefits. The example of this project has a good reference significance to the application of multi-machine lifting in construction.

【關键词】景观桥安装;4机抬吊;同步提升;起重验算

【Keywords】landscape bridge installation; four-machines lifting; synchronized lifting; lifting checking

【中图分类号】U445.4                                             【文献标志码】A                                                 【文章编号】1673-1069(2021)06-0161-02

1 项目概况

该项目为连接2栋建筑的人行景观天桥。景观桥分三跨布置,全长94m。景观桥呈“S”形状不规则变化。桥面两端头宽为4.8m和7m,中跨桥墩处桥面宽为11m。桥体采用钢结构箱梁为主梁,H型钢为次梁。桥体上方全长设置玻璃雨棚,桥墩上方设置2座杜鹃花柱。

2 桥体安装分解及说明

桥体钢构采用汽车吊安装,桥体共划分为A、B、C 3个区及D、E 2个异形块,整体安装顺序为:主墩1、主墩2安装→D、E异形块安装→A区桥体安装→B区桥体安装→C区桥体安装。本文通过选取C区桥体安装,探讨四机吊装在该项目中的应用。

C区桥体为该桥中跨段,施工采用原位散装,整体吊装。四机抬吊法,属于常规起重设备多机抬吊,施工经验成熟,大部分工程量在地面上完成,避开了高处作业,提高了安全系数,降低了焊接难度,对整个项目的安全、桥体关键焊缝的焊接质量控制提供了有力的保障。另外,采用四机整体抬吊相较于常规的高空散装,在经济及工期上也产生了明显的效益,项目完工后经初步估算,节约机械成本5万元,工期缩短了10天。

3 吊装设备的选择

登录APP查看全文

猜你喜欢

施工
后浇带施工技术在房建施工中的运用
铝模板在高层建筑施工中的应用
后浇带施工技术在房建施工中的践行探索
新型环保建筑材料在土木工程施工中的应用
防渗漏技术在民用建筑施工中的应用
后浇带施工技术在房建施工中的应用
后浇带施工技术在房建施工中的应用
土木工程施工技术创新探讨
防渗漏施工技术在房建施工中的应用
土木工程施工实习的探讨与实践