AP1000核电机组主发电机穿转子方案优化
2021-04-13赵瑞生
赵瑞生






摘要:在首台AP1000机组建造之前,三菱重工设计的该型号电机施工设计方案尚没有经过充分的实践验证,其转子穿装设计方案存在一定的缺陷和不足。為了优化AP1000核电机组主发电机穿装子方案,本文通过全球首台AP1000核电机组主发电机安装施工实践经验,从转子吊装、滑架拆除等方面提出了发电机穿装子方案的优化措施,通过发电机组安装施工的进一步验证,证明了这些优化措施的有效性。
关键词:AP1000 发电机 穿转子 优化
Optimization of AP1000 Nuclear Power Plant Main Generator Passing Through Rotor Scheme
Zhao Ruisheng
(China Nuclear Power Co.,Ltd.,Shanghai,200040 China)
Abstract:Before the construction of the first AP1000 unit, the construction design plan of this type of motor designed by Mitsubishi Heavy Industries has not been fully verified by practice, and its rotor installation design plan has certain defects and deficiencies.For the purpose to modify the insertion scheme of main generator rotor of AP1000 nuclear power plant, based on the main generator construction experience of the world’s first AP1000 unclear power plant, form aspects of rotor lifting and slide block removing, proposing the modified measures for the main insertion generator scheme. These modified measures were proved effective and useful by the real generator construction.
Key Words: AP1000; Generator; Rotor insertion; Modification
发电机穿转子施工是大型发电机组在电厂建造环节进行现场发电机组装的关键工序。转子穿装工艺较为复杂,所使用的专用工具较繁多,安装精度和清洁度控制要求较高,施工安全风险较大。
首台AP1000核电机组主发电设计和供货为日本三菱电机,该型号发电机机转子净重203t,全长17.1m,最大直径1.96m,具有单件重量大、尺寸长、结构紧凑的特点。
在首台AP1000机组建造之前,三菱重工设计的该型号电机施工设计方案尚没有经过充分的实践验证,其转子穿装设计方案存在一定的缺陷和不足。如穿装子方案中使用吊梁吊装转子的方案设计存在缺陷、转子滑架拆除困难等问题。本文结合国内某首台AP1000核电主发电机穿转子设计方案,通过实际建造经验分析了该方案存在的问题,提出了针对方案的优化措施,并在实际施工实践中进行了有效的验证,为同类型电力工程大型发电机穿抽转子作业提供了借鉴。
1.P1000核电机组发电机概况及穿转子工艺……p>