基于模糊综合评价的PPP项目风险量化评估与应用
2020-07-31余建福
余建福



摘要:近年来,国家在基建领域广泛采用PPP模式,有效增加了公共服务的融资渠道,激发了市场活力。因政府层面的PPP法律体系及政策保障还不完善,部分地方政府热衷包装伪PPP项目,加上社会资本的风险管控体系尚未成熟,众多PPP项目整体风险逐渐显现并加大,体现在不同领域、不同实施阶段。在此形势下,本文以社会资本角度采用模糊综合评价做PPP项目风险量化评估,并进行案例分析,有利于提高風险管理水平,有较强的实践价值。
关键词:PPP模式、PPP风险、模糊综合评价
Abstract: China has widely adopted PPP mode in the field of infrastructure construction over the years, which has effectively increased the financing channels of public services and stimulated market vitality. Due to the imperfect legal system and policy guarantee of PPP at the government level, some local governments tend tomake fake PPP projects. Coupled with the immature risk control system of social capital, the overall risk of most PPP projects gradually appears and increases, which is reflected in different fields and different implementation stages. Under this situation, it adopts fuzzy comprehensive evaluation in this paper to make quantitative risk assessment of PPP project from the perspective of social capital. In addition, it carries out case analysis, which can help the improvement of the level of risk management and is of great practical value.
Key words:PPP mode, PPP risk, fuzzy comprehensive evaluation
1引言
PPP模式广泛应用的同时,以央企为代表的社会资本迅速参与到国家基建领域PPP项目,为提供优质公共产品及公共服务做出了贡献,也实现了企业发展及业务转型。然而在PPP的建设热潮中,部分地方政府策划的项目不合规、实施方案设计不合理、融资保障不到位,导致部分PPP项目风险较高。社会资本也在项目管控中出现了问题,突出体现在风险评估流于形式,不能根据进展定期评估项目风险。因此在PPP项目推进的关键阶段,有效使用科学方法对项目进行风险量化评价,能够为企业管理提供决策依据,具有重要的实践价值。
目前国内外对PPP项目风险量化评估有较多的研究,王上铭等采用层次分析法构造风险评价模糊矩阵,对项目融资风险进行了量化评估[1]。戴大双等将BOT项目分为可量化风险和不可量化风险,可量化风险采用风险发生概率与项目影响程度的乘积进行计算[2]。……