地铁项目车站主体结构与附属结构交汇处围护结构拆除工艺研究

2020-06-09周虎

周虎

【摘  要】地铁施工中,车站附属结构通常在车站主体结构后施工,附属结构与车站交界处存在原有主体围护结构,为打通附属结构与主体结构,交汇处主体围护结构需要拆除。根据附属结构的受力要求,部分车站附属结构设计支撑对撑到交汇处主体围护结构、附属支撑以及交汇处主体围护结构的拆除存在高风险,对车站主体结构与附属结构交汇处围护结构拆除工艺进行研究是必要的。

【Abstract】In subway construction, the subsidiary structure of the station is usually constructed after the main structure of the station. The original main enclosure structure exists at the intersection of the subsidiary structure and the station. In order to get through the subsidiary structure and the main structure, the main enclosure at the intersection needs to be dismantled. According to the stress requirements of the subsidiary structure, the design support of some subsidiary structure of the station is of high risk to the dismantling of the main support structure, subsidiary support and the main enclosure structure at the intersection, so it is necessary to study the demolition process of the enclosure structure at the intersection of the main structure and the subsidiary structure of the station.

【關键词】附属结构;交汇处围护结构;拆除

【Keywords】subsidiary structure; enclosure structure at the intersection; demolition

【中图分类号】TU64                               【文献标志码】A                                   【文章编号】1673-1069(2020)02-0184-03

1 工程背景

石湾站1号风亭为异形风亭,共设置2道混凝土支撑(600mm×800mm)。支撑设计时考虑基坑受力将附属与主体结构冠梁采用中间支撑连成一体。因1号风亭支撑与主体结构冠梁相连接,车站主体围护桩不能提前拆除,导致风亭主体结构分多块施工。为完成附属主体结构的施工,需要结合基坑受力和支撑影响全面考虑施工工艺及流程。支撑设计如图1所示。

2 正常情况施工工艺

地铁施工中,一般附属围护结构设计阶段尽可能在附属与主体交汇处不设置支撑,方便交汇处围护结构破除以及附属主体结构的施工[1]。按照不设置支撑的情况整体施工流程为:围护结构拆除→底板施工→第二道支撑拆除→侧墙施工→顶板施工→第一道支撑拆除。

附属结构无支撑对撑到主体结构冠梁时,附属结构整体施工工艺流程衔接顺畅,所有工序一步到位,附属主体结构可以一次浇筑成型,基坑防水效果好,安全风险小,能够快速实现基坑封闭。……