平顶直墙暗挖密贴下穿既有车站施工的运用分析与研究

2020-02-29李余江

科技创新与应用 2020年7期

李余江

摘  要:文章以成都地铁某工程采用平顶直墙大断面暗挖法密贴下穿既有线车站施工为背景,提出并分析各设计施工方案优缺点,对本工程采用的施工步序、施工工艺及其施工要点等进行研究总结;同时利用有限元计算分析新建暗挖对既有车站的沉降影响,并与实际监测进行对比分析,验证了该设计施工方案的合理性。为今后类似重大工程的设计和施工提供参考。

关键词:平顶直墙;暗挖;密贴下穿;既有线;监测

中图分类号:U455 文献标志码:A         文章编号:2095-2945(2020)07-0046-04

Abstract: This paper puts forward and analyzes the advantages and disadvantages of each design and construction scheme based on the background of the construction of the station under the existing line by the concealed excavation method with flat roof and straight wall in a Chengdu subway project. the construction sequence, construction technology and construction key points adopted in this project are studied and summarized. At the same time, the influence of the newly built underground excavation on the settlement of the existing station is analyzed by finite element calculation, and compared with the actual monitoring, the rationality of the design and construction scheme is verified. It provides a reference for the design and construction of similar major projects in the future.

Keywords: flat roof straight wall; underground excavation; close penetration; existing line; monitoring

平顶直墙暗挖工法是在隧道因特殊外部条件无法按传统拱形断面实施时,采取的一种特殊施工工法;与传统拱形断面工法比较,该工法可以暗挖方式实现平顶直墙结构断面,其技术特点导致其在风险控制、沉降控制、进度控制等方面有一定劣势[1]。但随着地铁工程的高速发展和施工技术的日渐成熟,新建地下工程采用平顶直墙暗挖密贴下穿既有车站区间隧道的情况越来越多,且对既有线的影响和挑战也越来越大,故对该方法的研究对后续类似工程具有重要意义。本文以成都轨道交通8号线一期工程倪家桥站负三层暗挖下穿既有1号线车站为例,浅谈平顶直墙暗挖法密贴下穿既有车站施工。

1 工程概况

新建成都軌道交通8号线一期工程倪家桥站与1号线、18号线进行换乘。其中8号线车站需在负三层暗挖大跨度下穿既有1号线车站,暗挖段初衬结构密贴既有1号线车站底板(图1),采用平顶直墙暗挖法施工,暗挖开挖宽度22.7m,开挖高度8.35m,长18.7m,暗挖段上半部分为中密卵石土层,下半部分为强风化泥岩,中风化泥岩位于暗挖底板下2~3m。……