极寒条件下地铁管片预制质量控制
2018-09-21翟宝生
翟宝生
【摘 要】论文以我国北方城市呼和浩特地铁一号线和二号线作为实验参考,对地铁管片预制控制在极寒条件下施展的技术进行分析。分别从以下几个方面讲述了在寒冷条件下混凝土管片预制施工中需要注意的问题:施工环境、施工准备、原材料选取、混凝土施工、管片的冬季养护以及成品管片存放等,分析后做出了报告。
【Abstract】 Taking the metro line one and line two of Hohhot, which is a northern city of China, as the experimental reference, the paper analyzes the technology of prefabrication control of metro segments under extreme cold conditions. The problems needed to be paid attention to in the prefabrication construction of concrete segments under cold conditions are described respectively from the following aspects: construction environment, construction preparation, selection of raw materials, concrete construction, maintenance of segments in winter and storage of finished segments, etc. The following report was made after the analysis.
【關键词】极寒条件;地铁管片;预制;质量控制
【Keywords】 extremely cold condition; subway segment; prefabrication; quality control
【中图分类号】U231+.3 【文献标志码】A 【文章编号】1673-1069(2018)06-0130-02
1 施工的环境背景
为了让施工设备能够在寒冷的冬季可以正常工作,就需要在还没有入冬之前对管片车间的各项关键设备展开全方位的检查工作。锅炉方面为了对产品的质量进行保障需要全天二十四小时供热,要及时按照车间的实际需求调整供气的用量。要确保让车间、拌合站以及混凝土拌合使用水的温度等可以达到要求标准。[1]在入冬以后从十月中旬开始到次年的四月中旬期间,每一天都要做好检测环境温度的程序,而且一个工作班的员工需要最少检测四次以上并且做好相关的数据记录,每个工作班的检测时间规定是:早上七点、下午一点、晚上七点和凌晨一点。
2 施工前的准备工作
极寒条件下的管片需要准备一些预防措施工作,尤其是当气候一连几天都到了零下五度的时候,就不能再使用平时的管片施工技术。具体需要准备的步骤如下:
①为了保障锅炉房可以维持正常工作,要将冬季施工所需要的一切材料都准备好,比如机具、设备、能源以及各种工程材料等。……