燃煤机组脱硫废水处理系统存在的问题及对策
2018-09-10胡昕
胡昕


摘 要:脱硫废水处理系统采用化学和物理综合处理的办法,以去除废水中重金属离子,并使废水得到澄清,达标后排放。脱硫废水的主要问题是弱酸性、悬浮物和重金属含量超标,不能直接排放,必须进行处理。因此,废水系统的运行可靠性直接影响脱硫设备的正常运行。本文重点针对湖北西塞山发电有限公司脱硫废水处理系统废水旋流器堵塞及离心脱水机故障等方面进行分析,并有针对性地制定相关运行对策,以提高脱硫废水系统运行的可靠性,确保环保设施稳定运行。
关键词:废水旋流器;pH值;离心脱水机;扭矩
中图分类号:X773 文献标识码:A 文章编号:1003-5168(2018)22-0030-03
Problems and Countermeasures of Desulfurization Wastewater
Treatment System for Coal-fired Unit
HU Xin
(Hubei Xisaishan Power Generation Co., Ltd.,Huangshi Hubei 435000)
Abstract: The desulfurization wastewater treatment system adopts the method of chemical and physical comprehensive treatment to remove heavy metal ions in the waste water, clarify the waste water, and discharge it after reaching the standard. Main problem of the desulfurization wastewater is a weak acid, suspended solids and heavy metals content exceeds bid, no direct emissions, must be treated, thus the operation reliability of the wastewater system directly affect the normal operation of desulphurization equipment. This paper mainly analyzed the blockage of the waste water cyclone and the failure of the centrifugal dehydrator in the desulfurization wastewater treatment system of Hubei Xisaishan Power Generation Co., Ltd., and formulated relevant operation countermeasures to improve the reliability of the desulfurization wastewater system and ensure the stable operation of environmental protection facilities.
Keywords: waste water cyclone;pH value;centrifugal dehydrator;torque
1 機组及脱硫系统概况
湖北西塞山发电有限公司一期工程装备2×330MW机组分别于2004年7月和12月投入商业运行。锅炉由武汉锅炉厂设计制造,配套贫煤四角切圆燃烧锅炉。2009年8月一期2×330MW机组完成脱硫改造并通过168试运行,两台机组的烟气脱硫工程均采用石灰石-石膏湿法烟气脱硫工艺技术,脱硫装置采用一炉一塔的模式。其中石膏脱水系统、事故浆液系统、废水处理系统为四台机组脱硫装置公用系统。2013年11月,#2机组贫改烟,同期进行引增合一及脱硫系统取消烟气旁路挡板门改造;2014年6月,#1机组脱硫系统取消烟气旁路挡板门。#1、#2机组分别于2017年12月和2017年2月完成超低排放改造并投运。
湖北华电湖北西塞山发电有限公司二期工程装备2×680MW机组分别于2010年12月和2014年4月投入商业运行。锅炉由武汉锅炉厂设计制造,配套直流锅炉。……