铁路建设项目概预算和计划统计管理
2018-06-06王静
王静
摘 要:铁路建设是一个系统工程,建设规模大、周期长、影响因素多。目前高铁铁路建造指标在普遍在1.5亿元/公里至3亿元/公里之间,一个项目投资少则几十亿多则上百亿,如何做好建设项目概预算和计划统计管理,科学决策、依法合规管好、用好这笔费用,为项目快速、有序推进提供有效资金保障,是每一个建设单位领导层必须认真思考和对待的问题。
关键词:铁路;概预算;计划统计;管理
中图分类号:F530.3 文献标志码:A 文章编号:2095-2945(2018)15-0195-02
Abstract: Railway construction is a systematic project with large scale, long period and many influencing factors. At present, the construction index of the high-speed railway is generally between 150 million yuan/km and 300 million yuan/km, and the investment for a project is several billion yuan or more. How to have a good performance in the construction project budget estimates and statistical management of the plan? It is a problem that every leadership of the construction unit must seriously consider and deal with making scientific decision, managing well according to law, and making good use of this expense to provide effective fund guarantee for the rapid and orderly advancement of the project.
Keywords: railway; budget; planning and statistics; management
本人鐵路建设管理单位从事概预算、计划统计工作已有12年,先后参与张集铁路、集包增建第二双线铁路、张唐铁路、张呼客专共3条国家Ⅰ级铁路和1条客运专线项目的概预算、计划统计工作,现结合工作实战经历,从铁路建设不同阶段,浅谈铁路铁路建设单位在项目概预算和计划统计管理一些注意事项和重点工作,以期待对读者有所启发和帮助。
1 概预算批复阶段
该阶段建设单位应跟踪项目概预算的审批过程,认真组织研究概预算的编制内容及相对应的施工方案、施工组织设计等;做到概预算清晰、详细,费用不缺项、不漏项,并与施工方案、施工组织设计相符合。以便施工过程中好控制投资及组织各参建单位进行施工,该阶段应重点应关注:(1)土石方运距费用是否具有可操作。主要是因为初步设计阶段选择的取土场不能用或是没有及时签订协议造成后期无法使用。建议在初步设计阶段应认真组织设计单位,调查研究取土场的选择并及时与地方国土等部门签订取弃土协议。……