单台辅变运行对机组的影响
2018-04-12凌杰
凌杰
【摘 要】秦二厂1/2号机组在正常运行时,由发电机经厂变向厂内的设备供电,辅变处于热备用状态,当主电网或者厂内的变压器(主变、厂变)故障时,则四条厂用6.0kV母线将会自动切向辅变供电,机组进入事故规程。在核电厂技术规格书中仅对两台辅变不可用做出明确的规定,并未对单台辅变的不可用做出明确的规定,本论文详细分析当机组出现主变向辅变切换的情况下,单台辅变运行将会做机组产生的影响。
【关键字】单台辅变;容量;事故;技术规格书
中图分类号: TM623 文献标识码: A 文章编号: 2095-2457(2018)04-0146-001
Single auxiliary operation of the crew on the impact
Ling Jie
(Nuclear Nuclear Power Operations Management Co.,Ltd.,Jiaxing,Zhejiang 314300,China)
【Abstract】During the normal operation of No.1/2 plant of Qin Plant,the power supply in the plant is changed from generator to plant. The auxiliary transformer is in hot stand-by state.When the main power grid or the transformer (main transformer, factory transformer) Failure, then the four plants with 6.0kV bus will be automatically tangential auxiliary power supply, the crew into the accident rules. In the technical specification of nuclear power plant, only two sets of auxiliary variable are not available to make a clear provision, not a single auxiliary variable is not available to make a clear provision, the paper detailed analysis of the main unit when the auxiliary transformer switch The case of a single auxiliary operation will be the impact of generating units.
【Key words】Single auxiliary change; Capacity; Accident; Technical specifications
秦二厂1/2机组在正常满功率运行时,由发电机经厂变向厂内的设备供电,当主电网故障或厂内的变压器(主变、厂变)故障时,则四条厂用6.0kV母线将会自动切向辅变供电,机组进入事故规程。
在核电厂技术规格书中对辅变的可用性有着明确的要求:当仅厂外辅助电源不可运行则必须在36小时内修复,并且补充要求:假如厂区内附加柴油机可运行则退防时限延长至7天,否则机组退防到RRA投入的双相中间停堆状态。技术规格书中仅对两台辅变不可用做出明确的规定,并未对单台辅变的不可用做出明确的规定。所以说,现在单台辅变的检修等原因造成的不可用并不能划入厂外辅助电源不可运行这一条,而且在技术规格书中也找不到相应的规定。辅助电源系统在正常运行时,有两条6.0kV母线分别向1、2号机组的四条6.0kV母线供电,并且各自带一台升压变压器供给25MW的电锅炉,两条母线之间设有母联开关。……