焦化厂钢结构涂层的失效及重涂
2017-10-11蔡佳兴范益郦锁云张万灵
蔡佳兴*,范益,郦锁云,张万灵
(南京钢铁股份有限公司,江苏 南京 210035)
焦化厂钢结构涂层的失效及重涂
蔡佳兴*,范益,郦锁云,张万灵
(南京钢铁股份有限公司,江苏 南京 210035)
为解决某焦化厂钢结构涂层失效的问题,现场调查了环境腐蚀因素、原防护措施及其失效状况。厂区存在硫化物、氮化物、粉尘等污染物,在原防护施工中存在基材表面除锈不彻底、涂料种类搭配不合理、维护周期不合理、涂层厚度不达标等问题。通过制定适合该焦化厂各区域腐蚀环境特点的涂装方案,并在涂装环节严格控制施工质量,可解决原钢结构涂装防护层提前失效的问题。
钢结构;涂层;提前失效;腐蚀防护
Abstract:Aiming to solve the failure of coatings for steel structures in a coking plant, the corrosion environment, existing protection measures and failure conditions were investigated on spot.Sulfide, nitride, dust and other pollutants were found in the atmosphere.There are some problems during the construction of previous corrosion protection measures, such as incomplete surface de-rusting, unreasonable combination of different types of paints, improper maintenance cycle, and insufficient coating thickness.The early failure of coatings can be solved by developing a coating scheme suitable for the corrosion environment of each area in the coking plant, and strictly controlling the construction quality during the coating process.
Keywords:steel structure; coating; early failure; corrosion protection
First-author’s address:Nanjing Iron and Steel Co., Ltd., Nanjing 210035, China
某焦化厂自建厂3年后,平均每年投入约300万元对厂区内户外钢结构涂层进行维护。然而涂层在1年左右就又会发生局部破坏,表面锈迹斑斑,甚至导致钢结构因腐蚀而发生结构断裂失效。鉴于该焦化厂从延长钢结构涂层服役年限及降低成本方面提出新的要求,笔者在对厂区环境和腐蚀状况进行细致调研后,结合厂区自身特点制定了合理的防护方案。本文对此进行了详细介绍,以供同行参考。
1 焦化厂的情况介绍
进厂煤经配煤粉碎后由皮带送至煤塔,再由加煤车送料至焦炉,干馏后产生焦炭和荒煤气,焦炭经熄焦塔由皮带送至用户,荒煤气经提炼加工出焦油、硫和粗苯后形成净煤气供用户使用。厂内煤场皮带支架,翻煤机,焦炉,加煤车,推焦车,拦焦车,熄焦车,熄焦塔,横管冷凝器,电捕焦油器,机械化氨水澄清槽,脱硫塔平台及栏杆,洗苯塔平台及栏杆,煤气管道,管道支架等钢结构设施均暴露于户外,需进行防腐蚀保护。……