关于静压桩基施工过程中的常见问题及处理方法

2017-06-22周文俊

中华建设科技 2017年5期
关键词:处理方法

周文俊

【摘要】静压桩基础在城市人口密集区施工的建筑中应用越来越广泛,此法对施工工艺要求高、工序复杂、影响施工质量的因素较多,施工中经常出现质量问题。对施工中存在的桩基质量问题的分析与处理,会影响建筑物的结构安全和使用寿命。本文针对某工程的桩基施工中出现的质量问题进行分析,查找原因并提出处理方法。

【关键词】静压桩;质量问题;原因分析;处理方法

Common Problems in Construction Process of Static Pressure Pile Foundation and Its Treatment

Zhou Wen-jun

(Zhejiang Southeast Construction Management Co., LtdHuzhouZhejiang313000)

【Abstract】The application of static pressure pile foundation in the construction of urban densely populated areas is becoming more and more extensive. This method has many problems in construction technology, complicated process and influence of construction quality. There are often quality problems in construction. The analysis and treatment of the quality of the pile foundation in the construction will affect the structural safety and service life of the building. In this paper, the quality of pile construction in a project to analyze the quality of the problem, find out the reasons and put forward the treatment.

【Key words】Static pressure pile;Quality problem;Cause analysis;Treatment method

1. 前言

静压桩施工工序多,工艺要求高。由于不需要使用泥浆做冲洗液,施工现场干净,不会排放废浆污染地表水和地下水,施工时噪音较小,因此静压桩施工对环境基本不造成污染。随着国家对环境保护的要求越来越严格,在所有的地基基础施工方法中,此法最适合于在城市人口密集的城市区域工程中采用。

2. 工程簡介

某会议中心及综合配套设施改造工程位于城中心繁华地带,四周为住宅和行政办楼,是一个集会议、宾馆、娱乐为一体的综合性公共建筑群。该工程占地面积123467平米,总建筑面积68091平米,其中地下一层,地上四层,由三个单体建筑通过两个大堂连成一体,建筑风格宏伟庄严。基础由中500mm预制混凝土离心管桩(PHC)和桩顶承台共同组成,设计桩数4308根,桩长13~33米不等,混凝土标号c80,采用的静压桩机型号400T和600T。以下结合本工程就桩基施工中经常遇到的质量问题、原因分析及解决方法进行探讨。

3. 施工中遇到的质量问题

(1)桩位偏差过大。

(2)桩身倾斜过大。

(3)桩身断裂。……

登录APP查看全文

猜你喜欢

处理方法
简析工业废水处理技术
浅谈交通事故现场及事后处理方法
软土地基基础上水利施工处理方法
矿井水资源可持续利用与处理技术研究
火电机组低压配电系统常见故障及处理方法
浅谈野外驻训常见涉法问题的处理
城市垃圾无害化处理研究
煤矿采掘工作面顶板管理问题的处理方法
浅析半伞式水轮发电机组上导油槽下油雾密封盒绝缘不合格处理方法及预防措施