简述超高压蒸汽管道系统联合吹扫主要步骤及控制
2016-11-10任德龙
任德龙



摘 要:大型石油化工联合装置中供空分装置蒸汽透平压缩机使用的超高压蒸汽管道系统,要求管道内洁净度很高,跨区域流程长,吹扫气源压力高,流量大。如何在确保安全质量情况下完成类似的管道系统联合吹扫,就必须要求各工序严守规程和方案要求进行操作,为了在短期内达到吹扫打靶检查合格的质量目标,我们在管道系统引蒸汽吹扫前就对须吹扫的管道系统进行了化学清洗,以清除管道内壁的大量的浮锈、颗粒和附着物。缩短蒸汽吹扫的实际工作时间,节约了蒸汽能源,工期和质量都得到了保证。
关键词:超高压;蒸汽透平机组;吹扫;打靶
Brief ultra-high pressure steam piping system jointly purge the main steps and control
Ren De-long
( Hualu Engineering Science and Technology Co., Ltd. Xi'an,710065 China )
Abstract: large petrochemical joint device for an air separation unit steam turbine compressor using ultra-high pressure steam piping system, requires pipe cleanliness is high, cross-regional flow, purge gas source pressure, flow. How to ensure the safety and quality similar joint purge piping system, each process must require adherence to procedures and programs to operate the purge targeting inspection and approval of the quality objectives in order to achieve in the short term, we cited the steam blowing in the pipe system sweep on the piping system to be purged before chemical cleaning to clear the pipe wall a lot of rust particles and attachments. Shorten the the steam purge actual work time saving steam energy, duration, and quality assurance.
Key words: high pressure; steam turbine unit; purge; shooting
1.概况
2007年5月神华煤直接液化项目先期工程由神华自备热电厂经由公用工程管廊至空分装置的所有高压蒸汽管道全部施工完毕。该蒸汽正常操作参数为温度535℃、压力9.0MPa,设计值分别为550℃、10.6MPa,正常操作流量(两套)295吨/小时。
为了缩短吹扫时间,已对该管道系统相关单元及空分装置界区内的超高压蒸汽管道进行联合酸洗及钝化处理完毕,合格。
联合吹扫管道不包括自备热电厂界区内的管段,该部分由自备热电厂自行吹扫,打靶合格后再与公用工程管廊界区处管道接点碰头,自备电厂确保向外部稳定供汽。
2.吹扫目的
清除管道内残留的杂质、浮锈等,以免杂物进入蒸汽透平造成透平叶轮、密封及其它零部件的损坏。
3.吹扫原则
厂区域内超高压蒸汽管道的吹扫打靶工作由厂区生产总体组织和指挥,各项目组、空分装置配合,由组织总承包单位和公用工程管廊施工单位负责吹扫过程中的具体操作。……