海上天然气生产平台水循环调试方案优化
2016-01-17王腾飞,张宏彬,廖强等
海上天然气生产平台水循环调试方案优化
王腾飞1,张宏彬2,廖 强2,范沥元3,张卫涛2
(1. 海洋石油工程(珠海)有限公司,广东珠海 519055;2. 海洋石油工程(青岛)有限公司,山东青岛 266520;3. 海洋石油工程股份有限公司,山东青岛 266520)
摘 要:海洋石油生产平台在建造阶段需要进行生产系统水循环调试,模拟正常的生产流程以检验生产系统的完整性和功能性,对于天然气田的生产平台,其生产系统压力高,同时存在气液两相,使得水循环试验条件苛刻,技术要求高。基于天然气平台生产系统水循环调试的安全性、可行性和经济性,通过现场实践——以丽水36-1CEP天然气生产平台生产系统的水循环流程模拟调试优化为例,从临时管线连接方式、氮气加注方案和仪表功能测试方案三个方面提出最优化调试方案,以期对此类调试工作产生指导和借鉴作用。
关键词:海上天然气生产平台;水循环调试;优化
中图分类号:TE934
文献标识码:A
DOI:10.3969/j.issn.1008-2336.2015.02.102
文章编号:1008-2336(2015)02-0102-05
收稿日期:2014-03-24;
作者简介:第一王腾飞,男,1985年生,工程师,学士,从事海洋石油工程项目工程师工作。E-mail:wangtf@mail.cooec.com.cn。
改回日期:2014-05-05
Optimization of Debugging Scenario for Water Cycle for Offshore Natural Gas Production Platform
WANG Tengfei1, ZHANG Hongbin2, LIAO Qiang2, FAN Liyuan3, ZHANG Weitao2
(1. Offshore Oil Engineering( Zhuhai) Co. Ltd., Zhuhai Guangdong 519055, China; 2. Offshore Oil Engineering(Qingdao)Co. Ltd., Qingdao Shandong 266520, China; 3. Offshore Oil Engineering Co. Ltd., Qingdao Shandong 266520, China)
Abstract:It is required to conduct debugging on water cycle in offshore production system during the stage of platform construction and to simulate normal production process in order to verify the integrity and function of the offshore oil production system. In the production platform in nature gas field, the pressure in production system is high, and there exist gas-liquid two-phase at same time. Therefore, the condition for debugging on water cycle system is very harsh, and technical requirements are very high. From the point of safety, feasibility and economic of debugging on water cycle system in nature gas production platform, field practice has been conducted in simulation of water cycle debugging on in offshore production system in Lishui 36-1 CEP nature gas production platform. The debugging scenarios have been optimized from the connection way of temporary pipes, adding scenarios of nitrogen and testing scenarios on instruments function. It is expected that this can provide a guidance and reference for debugging on water cycle in this type of offshore oil production system.
Keywords:offshore natural gas production platform; debugging on water cycle; optimization
海洋石油生产平台在建造调试阶段,根据详细设计要求会进行水循环模拟调试,水循环模拟调试是用水、压缩空气或氮气模拟井产流体、由压力源向流程输入压力,投入尽可能多的流程设备和仪表,建立与正常操作时尽量相同的压力、温度、流量,模拟正常生产,并在水循环过程中,对控制仪表和关断系统进行调试[1]。
一般情况下,工艺生产系统、计量系统、原油处理系统、原油外输系统、注水系统应进行水循环试验[2]。……