己衣水库除险加固设计过程及工程效益评价
2016-01-15谢庆明,盛高学,陈天宝
己衣水库除险加固设计过程及工程效益评价
谢庆明1, 盛高学2, 陈天宝2
(1.云南省水利水电勘测设计研究院, 昆明650021; 2.云南省武定县水务局, 云南 武定651600)
【摘要】己衣水库位于云南省武定县境内的的金沙江南岸一级支流己衣大河的法保峡谷,是一座以灌溉为主,结合人畜饮水的省属重点中型水利工程。文章分析了该水库病害原因,介绍了大坝、泄洪设施、输水隧洞除险加固处理措施方案和工程实施后取得的效益。
【关键词】己衣水库; 除险加固; 措施; 工程效益评价
中图分类号:TV697.3文献标志码: B
Jiyi Reservoir Danger Elimination and Reinforcement Design
Process and Project Benefit Evaluation
XIE Qing-ming1, SHENG Gao-xue2, CHEN Tian-bao2
(1.YunnanWaterConservancyHydropowerSureyandDesignInstitute,Kunming650021,China;
2.YunnanWudingCountyWaterAuthority,Wuding651600,China)
Abstract:Jiyi Reservoir is located in Fabao Canyon of grade I tributary Jiyi River on South Bank of Jinsha River in Wuding County of Yunnan Province. It is a provincial key medium-sized water conservancy project combining human and animal drinking water based on irrigation. In the paper, disaster reasons of the reservoir are analyzed, danger elimination and reinforcement handling measure plan of dam, spillway facilities and water delivery tunnel, and benefits achieved after project implementation are introduced.
Keywords:Jiyi Reservoir; danger elimination and reinforcement; measure; project benefit evaluation
1工程概况
己衣水库位于云南省武定县己衣乡,地处长江流域的金沙江南岸一级支流己衣大河的法保峡谷。水库除险加固后,枢纽工程由碾压堆石加高坝体、新建泄洪隧洞、改建输水隧洞进口竖井组成;水库坝址以上径流面积100km2,总库容1260.2万m3,最大坝高85.2m,坝顶长140m,是一座以灌溉为主、结合人畜饮水的省属重点中型水利工程。
2工程病害情况[1-2]
己衣水库于1978年5月26日采用定向爆破筑坝技术,一次爆破堆积成坝,实际使用炸药752t,爆破土石方147万m3,上坝率81%,单位耗药量0.63kg/m3。爆破堆积平均厚度83m,最低马鞍点坝高74m,坝顶长约140m,底宽约410m,上下游平均坝坡比约为1∶2.5,是国内外定向爆破筑坝一次爆堆最高、上坝单位耗药量较省、坝体成形较好的工程。爆破后坝体堆积物为两岸爆破形成的碎块石、滚石夹少量碎石土,一般块径30~50cm,最大达5m以上,岩性主要为薄~中层状白云岩,其次为页岩、泥灰岩及硅质灰岩,强~弱风化,结构松散,架空现象十分明显。……