摘要:厦门高集海堤原水管道迁改工程中的过海管位于厦门大桥与高集海堤之间,过海管采用顶管方式施工,顶管线路上存在礁石,这些礁石需进行爆破清除。在水下礁石爆破施工过程中,要求确保厦门大桥、高崎村民房、高集海堤原水输水槽等建筑物、中华白海豚的安全。由此,采用台阶小规模爆破、毫秒延时逐孔起爆、不偶合装药结构等技术措施,实现了安全、保质、按期完成炸礁的目标。

关键词:炸礁;抛掷爆破;地震波;毫秒延时;台阶;不偶合装药;水中冲击波;

Underwater reef blasting of Xiamen Gaoji seawall water pipe migration project

Huang-Zhiwei

Waterway administration of Wuzhou,Guangxi Pro.

Abstract: The pipe which was over Xiamen Bridge and Gaoji Seawall in Xiamen Gaoji Seawall water pipe migration project, the pipe took the way of pipe jacking construction, there was rock on the line which need to remove by blasting. During the blasting process, it need to ensure the safety of Xiamen Bridge、the houses in Gaoqi village、water tank, the Chinese white dolphins.

So it took technical measures of the steps small blasting、millisecond delay by hole blasting、Non-coupling charging and so on. Achieve the goal of safety、quality and finishing the project on time.

Key words: reef blasting seismic wave millisecond delay steps blasting non-coupling charging the water shock wave

1 工程概况

厦门高集海堤原水管道迁改工程是厦门市重点引水工程,起自北溪引水集美泵站和集美水源泵站,终点接厦门本岛现有原水渠道和管道,其中过海段长1905m,位于厦门大桥与高集海堤之间,陆上段接北溪引水集美泵站和集美水源泵站管道位于集美区、接厦门本岛高崎渠道和管道的管道位于湖里区。本工程供水规模96万m3/d,包括:过海管、集美端陆上管线、高崎端过海管与渡槽及管道联络三部分,管道采用顶管、沉管和直埋等方式施工。

其中过海线路大部分采用顶管法施工,顶管长度1635m,沉管长度270m,双管布置,管道总长3810m,管径2200mm。顶管需穿过海泥、泥土和岩石;但是,线路中大量的岩石需预先爆破清除。

顶管线路中岩石长度约65m,两条线相距2m,需爆破底宽度为10m、底标高-12m的沟槽,需爆破岩层平均厚度约(包括超深)3.5m,最大深度6.7m,爆破量约2500m3。另高崎端2#工作井约-6m后也存在岩石,约有7.0m厚度的岩层,工作井直径15m,工程量约3200m3。……

登录APP查看全文

猜你喜欢

施工
后浇带施工技术在房建施工中的运用
铝模板在高层建筑施工中的应用
后浇带施工技术在房建施工中的践行探索
新型环保建筑材料在土木工程施工中的应用
防渗漏技术在民用建筑施工中的应用
后浇带施工技术在房建施工中的应用
后浇带施工技术在房建施工中的应用
土木工程施工技术创新探讨
防渗漏施工技术在房建施工中的应用
土木工程施工实习的探讨与实践