高填方铁路路基沉降注浆加固处理分析

2015-05-30潘朝锋

中华建设科技 2015年8期

潘朝锋

【摘 要】通过张集铁路小蒜沟段高填方路基沉降处理的工程实例,介绍了注浆法的工作机理,阐述了压力注浆法的施工流程及注意事项,并通过施工后的路基沉降观测,得出压力注浆加固法在处理高填方路基沉降方面效果良好,质量稳定。

【关键词】高填方;铁路路基;沉降;注浆加固

High embankment railway embankment settlement grouting reinforcement analysis

Pan Chao-feng

(Kehua St. Geotechnical Engineering (Beijing) Co., Ltd. Shanxi branch Taiyuan Shanxi 030045)

【Abstract】Through xiaosuangou period of the ZhangJi railway of high fill embankment settlement with engineering example, this article introduces the working mechanism of grouting method, this paper expounds the pressure grouting method construction process and the matters needing attention, and through the construction of subgrade settlement observation, it is concluded that pressure grouting reinforcement method in the treatment of high fill embankment settlement aspects effect is good, stable quality.

【Key words】High embankment;Railway;Grouting reinforcement;Settlement

1. 工程概况

张集铁路东起河北省张家口市既有京包线张家口南站,西至内蒙古自治区乌兰察布市,与既有京包线集宁南站接轨,为京兰通道的一部分,线路全178.009 Km。2010年7、8月份在铺架单位将线路细调完善后,8月下旬至9月中旬张家口地区普降大暴雨,雨量大,持续时间长。9月底雨季过后,在线路检查过程中,发现局部路基有沉降现象,随即总包单位组织各项目部人员对管段内所有的路基进行全面排查,并进行测量观测。期间,共发现16处路基下沉段,根据测量结果,小蒜沟车站站场路基段DK47+595~DK47+680、DK47+770~DK47+820两高填方段沉降量较大,两段最高填方高度分别为22m和31m,最大沉降量分别为10cm和11.3cm。

2. 沉降原因分析

经过对路基沉降原因进行认真细致的分析研究,路基下沉的主要原因是:

(1)两段高填方路基施工时间为2008年下半年,路基预留沉降量不足,2009年张家口地区气候干旱,雨季不完整,2010年8、9月份,本地区连降大到暴雨,降水量远大于往年,造成路基沉降量过大。

(2)排水系统对降水量估计不足,路基两侧排水沟未延伸至线路外侧,导致降水无法及时排除路基,造成雨水渗入路基本地,导致路基下沉。……