Bicriteria Scheduling on Single Machine with Outsourcing
2015-02-10CHENRongjunQINLizhenTANGGuochun
CHEN Rong-jun,QIN Li-zhen,TANG Guo-chun
(1.School of Science,Changzhou Institute of Technology,Changzhou 213002,China;2.Institute of Management Engineering,Shanghai Second Polytechnic University,Shanghai 201209,China)
Bicriteria Scheduling on Single Machine with Outsourcing
CHEN Rong-jun1,2,QIN Li-zhen1,TANG Guo-chun2
(1.School of Science,Changzhou Institute of Technology,Changzhou 213002,China;2.Institute of Management Engineering,Shanghai Second Polytechnic University,Shanghai 201209,China)
Scheduling with outsourcing is studied in this paper.It is assumed that both manufacturer and subcontractor have a single machine to process n jobs.The manufacturer needs to determine simultaneously a set of outsourced jobs and the schedule of the jobs in-house such that two criterias,i.e.,outsourcing cost and production cost,are minimized. The production cost is measured by the number of tardy jobs or the total tardiness of jobs in-house,and the outsourcing cost is proportional to the total processing time of jobs outsourced.Two kinds of problems with diferent criterias are considered.We analyze the computational complexity and provide pseudo-polynomial time optimization algorithms for the NP-hard version of the problems.
scheduling;outsourcing;bicriteria
§1. Introduction
Outsourcing is commonly required as a way to improve productivity in various companies. By outsourcing some jobs to a subcontractor,a manufacturer can make its production plan more fexible,meet the delivery deadlines of jobs and reduce its production cost.However,in making outsourcing decisions,the manufacturer will charge the subcontractor an amount of outsourcing cost.Thus,in order to maximize its net proft,the manufacturer needs to determine which jobsshould be outsourced,which jobs should be produced in house and furthermore,determine the schedule of jobs in-house.
As we know,scheduling with outsourcing in supply chain has received lots of attention in logistics and manufacturing management research.In the following,we briefy introduce single-stage production model.In 2005,Cai et al[1]were concerned with a problem where a manufacturer has to complete a number of orders received from the customers.Due to the capacity limit,the manufacturer has to subcontract a certain set of jobs to a third party for processing.They investigated the model that involves two machines,with one being a machine owned by the manufacturer and the other by the third party.The available time slot on the third-party machine each day is extendable,with an extra cost.Transportation time to have a job processed by the third-party machine is also considered.The objective is to minimize the total cost,including the lateness cost,the cost to use the third-party machine,and the overtime cost.The problem is shown NP-hard and properties on this model are obtained.Algorithms to fnd optimal solutions are developed.Motivated by a problem commonly faced by timesensitive product manufacturers,Chen and Li[2]proposed an analytical model to study the joint decisions of subcontracting and detailed job scheduling.In the proposed model,a manufacturer operates in a make-to-order fashion and receives a set of orders from its customers at the beginning of the planning horizon.The orders can be either processed by the manufacturer in-house or subcontracted to one of several available subcontractors,possibly at a higher cost. The manufacturer needs to determine which orders should be produced in-house and which orders should be subcontracted.Furthermore,it needs to determine a production schedule for the orders to be produced in-house.The objective is to minimize the total production and subcontracting cost,subject to a constraint on the maximum completion time of the orders. They analyzed the computational complexity of the model,developed a heuristic for solving it and analyzed worst-case and asymptotic performances of the heuristic.Qi[3]addressed a new scheduling model for a frm with an option of outsourcing.A job can be processed by either in-house production or outsourcing.All outsourced jobs have to be transported back to the frm in batches,and the transportation costs have to be taken into account.He modelled the situation as a scheduling problem with transportation consideration,discussed four common used objective functions,and solved them with dynamic programming algorithms.Lee and Sung[4]considered two single-machine scheduling problems with outsourcing allowed where each job can be either processed on an in-house single-machine or outsourced.It includes the problem of minimizing maximum lateness and outsourcing costs,and that of minimizing total tardiness and outsourcing costs.The objective is to minimize the weighted sum of the outsourcing cost and the scheduling measure represented by either one of maximum lateness and total tardiness,subject to outsourcing budget.It is proved that the problem is NP-hard.Some solution properties are characterized to derive heuristic algorithms,and also a branch-and-bound algorithm.They[5]also considered a single-machine scheduling problem with outsourcing allowed.The objective is to minimize the weighted sum of the outsourcing cost and the scheduling measure represented by the sum of completion times,subject to outsourcing budget.In the problem analysis,it is proved that the proposed problem is NP-hard in the ordinary sense,and some solution properties are characterized.Therewith,two associatedheuristic algorithms and the branch-and-bound algorithm are derived.In 2013,Zhong and Huo[6]studied a scheduling model in which each job can be processed in-house on a single machine or subcontracted to a subcontractor.If a job is subcontracted,its processing cost is diferent from the in-house cost and its delivery leading time is a stepwise function of the total processing time of outsourced jobs.Two objective functions are studied(1)to minimize the weighted sum of the maximal completion time and the total processing cost and(2)to minimize the weighted sum of the number of tardy jobs and the total processing cost.For the two problems,they proved the NP-hardness and developed pseudo-polynomial time algorithms.
In addition to the above-mentioned single-stage production model,there is also literature on complex foor shop environment,which can be seen in[7-14].We omit the detailed introduction here.
In this paper,we study an analytical model of bicriteria scheduling with outsourcing allowed. It is assumed that both the manufacturer and the subcontractor have a single machine.If a job is processed in-house,it will take an amount of production cost.Otherwise,it will be outsourced to subcontractor and an amount of outsourcing cost occurs.The decision maker will determine the outsourced jobs and the schedule in-house such that the two criterias,i.e., production cost and outsourcing costs,are minimized simultaneously.The rest of this paper is organized as follows.In Section 2,we provide a formal description of our problems.We show the computational complexity and propose pseudo-polynomial time algorithms for our problems in Section 3 and Section 4.we conclude our paper in Section 5.
§2.Problem Description
Suppose a manufacturer has a single machine for processing a set of jobs N={1,2,···,n} received from customers.pj,djare the processing time and due date of job j,respectively. Once jobs are processed in-house,an amount of production cost,i.e.,γ1,will be required.To make the jobs complete earlier,the manufacturer can outsource some jobs to a subcontractor for processing,which also has a single machine.If job j is outsourced,the manufacturer will pay for the subcontractor an outsourcing cost xpj,where x is the unit price of subcontractor’s machine time.Let γ2be the total outsourcing cost.

and assume that all jobs are available at time zero and no preemption is allowed.The objective is to minimize the production cost γ1and outsourcing cost γ2,simultaneously.In order to specify our problem,we follow the classical three-feld notation to denote our model as α1,α2|outsourcing,β|γ,where α1,α2describe the manufacturer’s and subcontractor’s machine environment,respectively.β describes constraints and γ is the optimizing criteria.
Since our problem has two criterias,we consider two types of our problem 1,1|outsourcing|(γ1, γ2)and 1,1|outsourcing|γ1+γ2.The problem 1,1|outsourcing|(γ1,γ2)is to identify the set of Pareto-optimal schedules(K,V),where a schedule S with γ1(S)=K and γ2(S)=V is called Pareto-optimal if there does not exist another schedule S'such that γ1(S')≤γ1(S)and γ2(S')≤γ2(S)with at least one of these inequalities being strict.
§3.The Problem with



ProofWe construct an instance with n jobs as follows.Set



Suppose there is a solution to P such thatbe the jobs in house and S2be the outsourced jobs.Thus,andThis is contrary to the former assumption.So,and Partition has a solution.


Lemma 1For 1,there exists an optimal solution in which all on-time jobs processed in-house are sequenced in the EDD order and all tardy jobs follow the early jobs.


The initial conditions for j=1 are the following

The Pareto-optimal set is determined from

For any given x,the overall running time of F1is in O(nP2).
AlgorithmF2
Step 1Renumber the jobs in EDD order.

Step 3Schedule the jobs of E in house.
Step 4For j∈T,then schedule j in-house and process it after E;otherwise, outsource it to subcontractor.

§4.The Problem with
Since the problem 1||Tjis NP-hard,we have


For j=1,2,···,n and V≤xPj,let Gj(a,V)be the total minimum tardiness for the frst j jobs such that the outsourcing cost is less than V and the total processing time of jobs in-house is a.We have the following recursions.

The initial conditions for j=1 are the following

The Pareto-optimal set is determined by

For any given x,the overall running time of F3is in O(nP2).

For j=1,2,···,n,let H(j,m,t)be the minimum value for the frst j jobs such that m jobs are scheduled in-house with the total processing time,i.e.,t,of the m jobs.We have the following recursions.

The optimal value is determined by

For any given x,the overall running time of F4is in O(n2P).
InstanceConsider three jobs with the processing times and due dates as follows.

Assume that x=1.For 1,1|outsourcing|we get the Pareto-optimal set{(2,0),(1,1), (0,2)}by F1.Using F2to solve 1,1|outsourcingwe obtain a feasible schedule S={1,3,2}with objective value 1,where all jobs are precessed in-house without any idle.
§5.Conclusion
In this paper we have studied logistics models that integrates single machine scheduling and outsourcing where the objective is to minimize the total outsourcing cost and production cost simultaneously.We showed the NP-hardness of problems and developed dynamic programming for the NP-hard versions.Future research topics may include the case with complex machine environment at manufacturer and more complex objective functions.
AcknowledgmentThe authors express their sincere gratitude to the reviews,whose constructive comments and suggestions led to substantial improvement in the paper.
[1]CAI Xiao-qiang,LEE C Y,VAIRAKTARAKIS G L.Optimization of processing and delivery decisions involving third-party machines[J].Nonlinear Analysis,2005,63:2269-2278.
[2]CHEN Zhi-long,LI Chang-lan.Scheduling with subcontracting options[J].IIE Transactions,2008,40: 1171-1184.
[3]QI Xiang-tong.Coordinated Logistics scheduling for in-house production and outsourcing[J].IEEE Transactions on Automation Science and Engineering,2008,5(1):188-192.
[4]LEE I S,SUNG C S.Minimizing due date related measures for a single machine scheduling problem with outsourcing allowed[J].European Journal of Operational Research,2008a,186:931-952.
[5]LEE I S,SUNG C S.Single machine scheduling with outsourcing allowed[J].International Journal of Production Economics,2008b,101:623-634.
[6]ZHONG Wei-ya,HUO Zhi-ming.Single machine scheduling problems with subcontracting options[J].Journal of Combinatorial Optimization,2013,26:489-498.
[7]LEE Y H,JEONG C S,MOON C.Advanced planning and scheduling with outsourcing in manufacturing supply chain[J].Computers and Industrial Engineering,2002,43:351-374.
[8]CHUNG D,LEE K,SHIN K,et al.A new approach to job shop scheduling problems with due date constraints considering operation subcontracts[J].International Journal of Production Economics,2005, 98(2):238-250.
[9]LIU Xiao,TU Y L.Capacitated production planning with outsourcing in an OKP company[J].International Journal of Production Research,2008,46(20):5781-5795.
[10]QI Xiang-tong.Two-stage production scheduling with an option of outsourcing from a remote supplier[J]. Journal of Systems Science and Systems Engineering,2009,18(1):1-15.
[11]QI Xiang-tong.Outsourcing and production scheduling for a two-stage fow shop[J].Int J Production Economics,2011,129:43-50.
[12]CHEN Rong-jun,TANG Guo-chun.Scheduling and subcontracting under parallel machines[J].Chinese Quarterly Journal of Mathematics,2012,27(4):590-597.
[13]CHOI B C,LEE K.Two-stage production scheduling problem with an outsourcing option[J].European Journal of Operational Research,2011,213:489-497.
[14]CHOI B C,CHUNG J.Two-machine fop shop scheduling problem with an outsourcing option[J].European Journal of Operational Research,2011,213:66-72.
O224
A
1002–0462(2015)04–0524–08
Received date:2013-09-26
Foundation item:Supported by the National Natural Science Foundation of China(70731160015);Supported by the National Natural Science Foundation of Jiangsu Province(yw06037)
Biographies:CHEN Rong-jun(1971-),male,native of Changzhou,Jiangsu,a professor of Changzhou Institute of Technology,Ph.D.,engages in scheduling and its application;TANG Guo-chun(1943-),male,native of Shanghai,a professor of Shanghai Second Polytechnic University,engages in scheduling and its application.
2000 MR Subject Classifcation:90B35,90C27
杂志排行
Chinese Quarterly Journal of Mathematics的其它文章
- The Interior of Numerical Ranges of Operators
- On the Transitivity of the Strong Product of Graphs
- Continuous Dependence of Bounded Φ-variation Solutions on Parameter for a Class of Discontinuous Systems
- On the Analog of Shephard Problem for Lp-polar Projection Bodies
- Some Approximation Properties of Certain q-Sz´asz-Mirakyan-Baskakov Operators
- The Group of Automorphisms of Transitive 2−(v,23,1)Designs