某深基坑开挖方案及稳定性分析
2012-10-19林建天
林建天
摘要:从技术、施工、经济等方面对王滩电站地下泵房深基坑开挖方案及开挖方法进行了讨论和比选,并结合计算机技术对不同开挖方法的过程进行了模拟计算分析,理论与工程实践结果表明,采用半放坡开挖(从地面标高3.5m到地下-9m)和地下连续墙(从-9m到-13.5m)相结合的方案,基坑稳定,施工简单、经济效益好,既保证了施工质量,也满足了工期要求,对同类工程的施工有一定的参考和借鉴价值。
关键词:深基坑,;开挖方案;稳定性分析
Abstract: This paper discussed and compared Wangtan power station underground pump station deep foundation pit excavation scheme and excavation methods from a technical, construction, economy and other aspects, and combine with computer technology do a simulation analysis on different excavation method of process, theory and engineering practice shows that, by using half slope excavation ( from3.5m to ground elevation underground -9m ) and underground continuous wall ( from - 9m to13.5m ) combining scheme, foundation stability, simple construction, good economic benefit, which not only ensures the construction quality, but also to meet the construction requirements, it has certain reference and reference value to the similar project construction.
Key words: deep foundation pit, excavation scheme, stability analysis
圖分类号:TU94文献标识码: A 文章编号:2095-2104(2012)03-0020-02
1、工程概况
本工程循环水泵房地下结构为埋深17.5m,内部尺寸57m×39.4m×16m的钢筋砼箱体结构,初步设计采用深36m,厚1.0m的地下连续墙支护结构。地连墙内衬钢筋砼叠合层,共同构成地下结构外壁,泵房内部与短边平行方向设有7道钢筋砼隔墙,将泵房分为8格相互独立的泵室。为了保证三号港池西岸线地基土的自身稳定,且不被海水带入循环水系统影响取水水质,在取水口南北两侧修建地下连续墙护岸,地下连续墙护岸分前墙和后墙两部分。前墙长度2*80m,深度36m,厚度1.2m。后墙长度2*80m,深度18m,厚度0.8m。前后墙间距40m,用100根拉结杆拉结,工程总工期7个月。本工程工期紧,任务重,技术难度大。
循环水泵房位于闲置废弃虾池和弃泥场,地面标高在4.2m左右。泵房所在地貌单元上均属滨海平原地带,地势平坦,施工场地宽阔。施工现场地层主要为第四系全新统海相沉积地层。
第一层(Ⅰ):为近代河流沉积或人工挖掘回填土,岩性主要为粉细砂、粉土,鱼塘底部沉积薄层淤泥。……