刍议大采高支架(高架)的组装与就位
2012-10-15安平舒
安平舒
摘要:目前,高架在煤矿的应用越来越广泛,一般5-6米的煤层采用高架支护的方式,可完成厚煤层一次采全高,这样单面产量高,安全状况好,生产成本低,是目前工作面支护的发展方向。可在支架的运输、组装、就位过程中存在一些难度,同时也值得我们去探讨。下面就我公司机修厂生产的ZY5000/25/50型液压支架为例进行探讨。
关键词:组装;布置;运输
Abstract: At present, elevated in the coal mines of the application more widely and elevated Supporting generally 5-6 meters of coal, to be completed by the thick Seam full height, so that the single-sided high yield, the security situation is good, the production cost is low, is the development direction of the face support. There is some difficulty may be in the process of stints transport, assemble, place, also worthy of us to explore. Here to explore our machinery repair production of ZY5000/25/50 of hydraulic support, for example.Key words: assembly; layout; transport
中圖分类号: U448.28文献标识码:A
一、散架运输
从地面到组装点都是散架运输,该支架整体重量为23吨,在地面解体为六件:即顶梁、掩护梁、两个立柱、四连杆和底座。将两个立柱和四连杆装一车共计四车。散架下井时根据组装好支架进工作面的方向不同,四车的运输顺序有所不同;若支架是定量朝前仅工作面,则四车的运输顺序为:顶梁—底座—四连杆(两个立柱)--掩护梁。若支架是定量朝后仅工作面,则四车的运输顺序为:底座—顶梁—四连杆(两个立柱)--掩护梁;同时还要考虑组装支架的方向来确定每车散架的入井方向。
二、组装峒室的规格和绞车布置
1、组装峒室的规格
经过计算和使用过程中的经验,组装峒室的规格长×宽×高为10米×5.5米×5.5米,这样在使用过程中有足够的空间,有利于组装过程的安全。
2、绞车布置
每个组装峒室至少有8台JM—14型绞车,其中4台为起吊绞车,另外2台为对拉绞车;为方便使用,可在两端再各加2台JM—14型绞车以备它用(一台用于从回绳站向组装点拉散架,另一台从组装点向工作面对拉支架)。(绞车布置见附图)……p>