城市建设理论研究 2012年16期

佘声伟

摘要:本文结合公路路基施工实例,为了有效地保证路基地面排水顺畅,在路基两侧设置了侧沟、排水沟等地面排水系统,在路基内及路肩上排水、防护工程施工同时与各专业设备、声屏障等相关工程与路基主体工程采取集成施工,提出其详细的施工流程,为同类工程提供参考指导。

关键词:公路施工;路基施工;路基防护;集成施工

Abstract: this paper highway subgrade construction practice, in order to effectively guarantee roadbed ground catchment is smooth, on both sides of the subgrade set side ditch, drain on the ground drainage system, in the roadbed and road shoulder in project construction and drainage, protection and the professional equipment, noise barriers and related engineering and roadbed the main body of the project to take integrated construction, puts forward the detailed construction process, provide a reference for the similar project instruction.

Keywords: highway construction; Subgrade construction; Roadbed protection; Integrated construction

中图分类号:X734文献标识码:A 文章编号:

工程概况

某公路本标段沿线通过太湖湖积平原,地形平坦、开阔,大部分辟为农田,水塘零星。所经地区均为第四系地层覆盖,厚度由西向东渐增,一般在50~330m,为冲洪积、湖积、海积或混合型成因,岩性以黏土、粉质黏土、淤泥质土、粉土及粉细砂为主。路基工程主要包括地基处理、路基填筑、路基防护以及过渡段结构为主要的路基加固及防护类型。同时为了有效地保证路基地面排水顺畅,在路基两侧设置了侧沟、排水沟等地面排水系统。本项目重点在于路基内及路肩上排水、防护工程等与各专业设备、声屏障等相关工程与路基主体工程采取同步施工。

路基排水、防护工程施工

在雨季,要做好路面排水系统的疏通,确保已施工的路基表面不积水。路基填筑按“四区段、八流程”的工艺进行,填筑路堤时,严格按照设计文件和规范要求设置沉降观测设施,进行沉降观测。采取多种措施严格控制路基工后沉降与不均匀沉降,根据沉降监测反馈信息,进一步完善工程措施,确保工后沉降达到设计要求。……