浅谈施工便道在山区管道安装施工中的作用和修筑方法
2012-04-29章邦伟
【摘 要】在山区进行长输管道施工,为了将大量钢管和施工设备运至施工作业带,顺应山势修筑施工便道对于保证管道安装任务按时完成至关重要。本文就一段陡坡安装实例,介绍了施工便道修筑方案,并指出了修筑施工便道的注意点。
【关键词】施工便道;降坡;顺应山势
Role in the construction and construction methods of the construction detour in the mountains pipeline installation
Zhang Bang-wei
(Oilfield Construction Department of Jiangsu Petroleum Exploration Bureau Jiangdu Jiangsu 225261)
【Abstract】Long-distance pipeline construction in the mountains, to a large number of steel pipes and construction equipment shipped to the construction work with, and conform to the mountain to build the construction of sidewalk completed on time is essential to ensure pipeline installation tasks. A period of steep installed instance, describes the construction of the sidewalk construction program, and pointed out that the attention to the point of the construction of the construction detour.
【Key words】Sidewalk construction;Down the slope;Conform to the mountain
1. 引言
中国的油气管道建设进入了高峰期,长输管道穿过沙漠,越过高山,跨过江河,向着全国各地延伸。在长输管道进入山区施工地段,山区地形复杂,有陡崖,有陡坡,有峡谷,有冲沟,那么在这些地区施工,要将大量的钢管以及施工设备运送到作业带,管道施工安装存在很大的难度。
要保证在这些地区顺利施工,将大量的钢管和施工设备运至作业带,首先要修筑施工便道,可见修筑施工便道在山区长输管道施工中起着重要的作用。
修筑施工便道遵循顺应山势的原则,既要保证安装施工顺利进行,又要尽可能减少占用山林、农田,保持和维护自然生态环境。
本文以某长输管道经过陡坡、陡崖修筑施工便道为例,简述施工便道的修筑方法和注意要点。
2. 施工便道修筑实例
由江苏油建承建的川东北至川西输气管道工程(平昌——元坝段)第v标段,工程地点在四川省阆中市境内,管线全长26.2Km,采用1016×17.5/21mm钢管,材质为X70,设计压力10MPa。
该标段管线位于大巴山腹地。管线走向随山峦起伏,从一个山顶下到山脚,穿过小溪上到第二个山顶,再下山如此重复,呈“W”状,其中已经施工的一处陡坡,桩号为NLZ009~NLZ011,位于阆中市三庙乡,此段管道长为220m,垂直高差为130m,管道沿线多为岩石地质构造,无直接便道可以通行。……